Proactive: Cyprium Metals advances Nifty copper restart as commissioning results strengthen outlook - ICYMI
Proactive
Cyprium Metals Ltd (ASX:CYM, OTCQB:CYPMF) last week outlined further progress towards restarting copper production at its Nifty Copper Complex in Western Australia, with encouraging heap leach commissioning results and key electrical infrastructure milestones supporting its target of producing first copper cathode in the fourth quarter of 2026.
Executive chairman Matt Fifield told Proactive that the company was transitioning its direct injection heap leaching operation into commissioning while completing pre-commissioning activities at the solvent extraction and electrowinning (SXEW) plant.
Fifield said early commissioning had confirmed the suitability of direct injection leaching for the existing Nifty heaps, following more than a year of technical assessment and field trials.
The operation had achieved targeted injection rates, with early copper recovery and acid consumption results meeting or exceeding modelled expectations.
"We saw an immediate response from putting acid into the heaps and generating copper at ratios that were, in fact, better than we had anticipated," Fifield said.
According to the company's latest operational update, copper concentrations in the off-flow solution had increased to approximately 1.3 grams per litre, while acid consumption averaged 4.25 grams per litre.
These results represented an important step towards building the solution grades required for processing through the SXEW plant, with the company targeting copper concentrations of at least 2.5 grams per litre.
Fifield also highlighted the progress made in establishing the production wellfield, which comprises 212 production and monitoring wells providing access to approximately 1.7 million tonnes of material.
Grade control sampling had reconciled within approximately 5% of the existing resource block model, providing further confidence in the underlying production assumptions.
Fifield said the established wellfield effectively covered the company's next six to eight months of planned production under conservative recovery assumptions.
"It's really more of a de-risking moment, with all of that production so quickly established," he said.
The company also reported progress towards commissioning the SXEW plant, with high-voltage power connected to its electrical infrastructure.
Fifield explained that installing programmable logic controller systems and energising the plant were among the remaining tasks before wet commissioning.
Looking ahead, key potential catalysts include the expansion of leaching operations, further improvements in copper solution grades, commencement of SXEW wet commissioning and production of the first copper cathode.
Successful completion of those milestones would represent significant progress in Cyprium's phased strategy to return the Nifty Copper Complex to production.
Fifield said the operational team remained focused on safely completing the remaining commissioning activities as the company advanced towards commercial production.
Read the full article here.