Nifty Heap Leach Mineral Resource Estimate
Released
Released
Announcement PDF
ASX ANNOUNCEMENT
19 August 2024
Nifty Heap Leach Mineral Resource Estimate
Cyprium Metals Limited (ASX: CYM) (Cyprium) is pleased to announce the 2024 Mineral Resource
Estimate (MRE) for the existing above-surface material stacked on the heap leach pads at the Nifty
Copper Mine (Nifty) in Western Australia.
Highlights include:
•
Indicated and Inferred Mineral Resource Estimate of 12.7 million tonnes grading 0.43%
Cu for contained copper of 54,050 tonnes
•
2021 sonic drill campaign incorporated into drill database
•
Potential for further upside as drill data does not extend to the bottom of the material
on the heap leach pads
“This is back-to-basics execution,” said Cyprium Executive Chair, Matt Fifield. “Restarting the
cathode plant is the next logical step for Cyprium’s new management team and the first phase of
Nifty’s redevelopment. To move towards operations, we need comprehensive and up to date
resource information. Our team produced this MRE by going back to first principles, organising and
incorporating all prior existing data, and including new analysis from the 2021 sonic drill program.
The result is the first updated MRE since 2015 for the unrecovered copper on Nifty’s heap leach
pads. It’s a strong foundation on which we can build our forward plans.”
The 2024 Heap Leach MRE defines an indicated and inferred copper resource containing approx.
54,000 tonnes of copper that is supported to JORC standards through drilling information – see
Table 1 below. A review of historic production data indicates that there is substantial potential
resource upside from unsampled stockpiled material. This unsampled material is not able to be
supported through drilling information as all drill holes were halted short of the pads to maintain the
integrity of the pad and liner.
The 2024 MRE incorporates new data from a 2021 sonic drill program which was run in support of
previous feasibility studies. Analysis of samples obtained from the sonic program have supported
important metallurgical inputs on the drilled resource.
Table 1 – MEC August 2024 Nifty Heap Leach Mineral Resource Estimate by Resource
Category.
Notes: zero Cu ppm cutoff grade, no top cut applied, numbers are rounded and may not add
ABN 48 002 678 640
T +61 8 6374 1550
ASX: CYM
Level 1, 437 Roberts Road
Subiaco, WA, 6008
www.cypriummetals.com
Drilled Mineral Resource
The 2024 Heap Leach MRE is the first update of an MRE on this material since 2015. The mineral
resource in Table 1 represents the portion of the stockpile that was estimated from drill data in
accordance with the JORC (2012) code.
An MRE was declared in 2015 after a series of internal studies during 2014 and 2015 were
accompanied by drilling and sampling campaigns. A comparison of the 2015 and 2024 drilled
resource estimates is presented in below:
Table 2 – Nifty Heap Leach 2024 MRE Versus 2015 MRE
In 2021, Cyprium conducted a 24-hole sonic drilling program. The 2024 MRE incorporates this data.
Figure 1 below shows the location of the drill collars from 2007 to 2021.
Figure 1 – Nifty Heap Leach Drill Hole Location
MEC Mining examined previous methods and information for adequacy under current code and
recommended a number of changes to classification and drill hole inclusion. Additional information
can be found in the accompanying MEC August 2024 Heap Leach MRE.
Cyprium Metals (ASX:CYM)
Page 2
Drilled Resource Excludes Stockpile Base
This estimation of the JORC resource, using drilled intercepts only, is likely to significantly
understate the amount of metal contained in the material on the heap leach pads as the drill holes
stopped an estimated depth of between 3 and 4 meters above the heap leach pad lining to protect
the integrity of the heap leach pad and liner. Therefore, a reasonable volume of material has been
excluded from the resource calculation which was reliant on drill data.
Figures 2 and 3 below show the 2024 MRE block model in cross section and oblique view. Red and
green areas correspond to drilled Indicated and Inferred resource. Blue areas correspond to
unsampled material.
Figure 2 – Nifty Heap Leach 2024 MRE Classifications (oblique view)
Figure 3 – Nifty Heap Leach 2024 MRE Classifications (section view)
Heap Leach Stockpile - Reconciliation to Production Records
Cyprium believes the best estimate of copper contained in the entire heap leach stockpile (e.g.
inclusive of unsampled material) is obtained through reconciling metallurgical accounting records
from prior operations. Experts from MEC reviewed the historical records and accounting approach
and believe that this a reasonable estimation methodology and appropriate for inclusion in
calculating total copper in the heap leach stockpile.
Cyprium Metals (ASX:CYM)
Page 3
Historical records show that 17.2 million tonnes of mined material was stacked on the pads at Nifty.
These tonnes contain 311,169 tonnes of copper in aggregate. Cumulative cathode production over
the prior operational life of Nifty was 217,124 tonnes from inception until cathode plant operations
ceased in 2009. The difference between these two figures (stacked and produced) is 91,140
tonnes.
“Looking back at the history of the site, we see that cathode production at Nifty stopped abruptly
when the new underground mine began,” said Fifield. “The owner at the time was primarily
interested in supplying feed to the concentrate market from the now abandoned underground mine.
The result was that the cathode plant was shut before its time, leaving unrecovered copper in the
heap leach material. This is Cyprium’s near-term commercial opportunity.”
This ASX announcement was approved by the Cyprium Board of Directors.
Further information:
Matt Fifield
John Gardner
Executive Chair
Investor and Media Relations
matt.fifield@cypriummetals.com
communications@cypriummetals.com
T +61 8 6374 1550
E communications@cypriummetals.com
Competent Person Statement
The information in this report that relates to the estimation and reporting of the Nifty Heap Leach Mineral
Resource Estimate dated 19 August 2024 is an accurate representation of the recent work completed by
MEC Advisory Pty Ltd. Mr Dean O’Keefe has compiled the work for MEC Advisory and is a Manager of
Resources for MEC Mining and a Fellow of the Australasian Institute of Mining and Metallurgy (#112948).
Mr O’Keefe has sufficient experience which is relevant to the style of mineralisation and type of deposit
under consideration and to the activity which she is undertaking to qualify as a Competent Person (CP). Mr
O’Keefe consents to the inclusion in the release of the matters based on this information in the form and
context in which it appears.
About Cyprium Metals Limited
Cyprium Metals Limited (ASX: CYM) is an ASX-listed Australian copper company. Its flagship property is
the Nifty Copper Mine in Western Australia, which previously produced significant copper from both oxide
and sulphide resources. Cyprium is focused on redeveloping Nifty, which has the advantage of significant
invested capital, data from a long operating history, large-scale resources, current operational approvals,
and recent investment in the property.
The Company’s other assets include significant copper-focused properties in the Paterson and Murchison
Provinces, including multiple defined resources.
Visit www.cypriummetals.com for further information.
Cyprium Metals (ASX:CYM)
Page 4
Material Information Summary
Please refer to Appendix 1 of the accompanying MEC August 2024 Heap Leach MRE for the full
JORC Table 1. A summary as required by ASX Listing Rule 5.8.1 is provided as follows:
Geology and Geological Interpretation
The Heap leach comprises ore mined and stacked from the Nifty mine. Stacking continued until the latter
part of 2008, and overall production ceased from the Heap Leach in 2009. The stacked Heap Leach
material is not insitu.There is no continuity of grade or geology within the stockpile.
There are approximately 60 stockpiles over 6 pads that comprise the Heap Leach. The dimensions of
each pad are ~350m long, 60-80m wide and 4-9m high. They were stacked in a westerly direction,
starting with pad 1, meaning the age decreases to the west.
From east to west the copper content decreases and changes from mainly silicified carbonate and shale
blends, through to chalcocite and multiple coarse rock types and shale blends.
For all drilling programs the drillholes were stopped around 4-5m above the base of the leach pad to
prevent penetration of the liners. Two surfaces were interpreted to constrain the Heap Leach – a
topographical surface for the top, and a base surface projected three meters below the deepest drillholes.
These two surfaces formed the geological interpretation for the Heap Leach and was used to constrain
the Mineral Resource estimate.
Drilling Techniques
The heap leach piles have been drilled over four drilling campaigns for the purpose of supporting an MRE
to establish tonnage and grade. Aditya Birla completed three separate RC drilling programs (2007, 2014,
2015). In 2021 a sonic drilling program was completed by Cyprium.
•
2007: The 2007 campaign targeted Pads 2, 3, and 4, with 124 RC drillholes, and reported a single
composite total copper assay per drillhole.
•
2014: The 2014 campaign targeted Pads 5 and 6 with 109 RC drillholes with 1m sampling,
assayed for total Cu only. During a site visit on 12 March 2020 the sample coarse rejects for
these drillholes were discovered in reasonable condition in a shipping container.
•
2015: The 2015 campaign targeted Pads 2, 3, and 4, with 41 RC drillholes. Samples were at 1m
intervals and were tested for total Cu only.
•
2021: A sonic drilling program was conducted in 2021 by Cyprium, targeting pads 3, 4, 5, and 6.
This consisted of 24 drillholes sampled at 1m intervals and tested for Ca, Co, Cu, Fe, Mg, Mn, S,
and Si.
Sampling and Subsampling Techniques
For the 2014 and 2015 RC drilling programs, and for the 2021 sonic drilling program, sampling was
conducted at 1m intervals. However, the 2007 RC program comprised a single composite sample for the
entire drillhole.
Sample collection for the 2014 and 2015 RC drilling programs was via a rig mounted cone splitter
attached to the cyclone. Two samples were collected for every 1m interval and labelled A and B. Sample
A was sent to the laboratory and sample B was retained.
For the 2021 sonic drilling program, single samples were collected.
Cyprium Metals (ASX:CYM)
Page 5
Sample Preparation
For the 2007 drilling a single sample (of up to 2.4kg) was collected for each hole.
For the 2014 and 2015 RC programs, 1.5-3.0kg of material was collected in a calico bag over a 1m
interval from the cyclone using a cone splitter. The samples were sent to ALS laboratory for preparation
(drying, crushing, splitting and pulverising) with a 50gm sample analysed using a 4-Acid ICPOES method
(ME-ICP62).
For the 2021 sonic drilling program, the majority of samples were obtained at 1m intervals.
Sample Analysis Method
The 2007 RC drilling samples were analysed by Inter Mountain Laboratories, Wyoming, USA. The
samples were split into three size fractions, and analysed for Cu. The total Cu value for the whole sample
was calculated as a weighted average of the results from the three size fractions. Three analyticals were
used: 4-Acid AAS for primary sulphide, copper in oxide by AAS after H2SO4 leach, and cyanide soluble
copper.
The 2014 and 2015 RC program samples were analysed by ALS laboratories in Perth using a 4-Acid
ICPOES method (ME-ICP62) for 16 elements: Ag, As, Ca, Cd, Co, Cr, Cu, Fe, K, Mg, Mn, Ni, Pb, S, Sb,
and Zn. Results exceeding the detection limit of the method were re-analysed with an ore-grade method,
e.g. Cu-OG62 for copper which is a 4-acid digest, but with a variable finish depending on the element.
For the 2021 sonic program, samples were analysed by ALS in Perth by XRF for Cu, Ca, Co, Fe, Mg, Mn,
S, and Si. In May 2024, 176 samples from 18 of the 24 sonic drillholes were re-submitted for analysis to
Bureau Veritas Laboratories in Perth. These samples were analysed using a 4 acid digest then ICP-OES
for Ca, Fe, Mg and S, and ICP-MS for Cu. The samples used to support the MRE were the samples
analysed by XRF, as this was a complete suite for all the sonic drillholes.
Estimation Methodology
RC and sonic drillholes were used for the grade estimation. The estimate was constrained by wireframes
representing the surface and the base of the heap leach stockpiles. The material is not in situ therefore
there was no geological or grade continuity. As such, no lode geological interpretation or domaining was
undertaken.
The estimation approach selected was Inverse Distance Weighting (IDW). A power of 3 was selected to
give more weight to local samples, no top cuts were applied. The block model was populated by
estimating into parent cells only, using two search passes to inform the estimate. All search ellipses were
orientated at a 0° azimuth, no plunge and a -90° dip.
Classification criteria
An Indicated classification was given to the block model where the MRE is estimated from the 2014 and
2015 RC drilling, the 2021 sonic drilling, and was supported by QAQC data.
An Inferred classification has been given to blocks supported by the 2007 drilling (which comprise a
single assay for the entire hole), on the periphery of the stockpile where it was not possible to drill due to
slope and proximity to the edge.
Pad 1 and the periphery of pad 2 is mineralised waste, due to the lack of drilling data. Where the drillholes
do not extend to depth (due to the risk of penetrating the leach pad liners) then the blocks are also
considered mineralised waste. All mineralised waste is unclassified material.
Cyprium Metals (ASX:CYM)
Page 6
Cutoff grades
The MEC August 2024 heap leach MRE is reported above a zero Cu cutoff, and no top cut was applied. A
zero economic cutoff grade is applied as the heap leach MRE is a global estimate. There is no local map
of grade variability, the remaining (unrecovered from previous operations) contained copper is estimated
within the entire stockpile. There is no selectivity that would permit the application of an alternative cutoff
grade. The ore was originally mined from the pit above an economic cutoff and stacked on the heap leach
and then copper was recovered from the stockpile, not all copper was recovered, with remaining copper
being the subject of the MRE.
Mining and metallurgical factors
Mining factors are not applicable, the Heap Leach ore was mined and stacked previously.
There are three main bodies of metallurgical test work that support Reasonable Prospects for Eventual
Economic Extraction (summarised in Table 3):
Table 3 – Recovery From Metallurgical Test Work Programs
Test Data Set
RMD Stem 3m Pilot Trial
(2009)
Metals X Limited
Sequential Leach Testing
(2020), Average
Cyprium Sequential Leach
Testing (2024), Average
48.3
45.2
50.3
Recovery of Total
Copper (%)
Metals X Limited 2020 sequential leach testing:
In 2020 Metals X Limited selected 10 holes from the 2014 drilling campaign for sequential leach analysis
from which 152 individual samples were selected and analysed for acid and cyanide soluble copper.
The resultant data set provided calculated recoveries with a mean of 45.2% and standard deviation of
11.5% (refer Figure 4).
Figure 4 – Heap Leach Recovery Distribution Curve (Metals X Limited Data)
Cyprium Metals (ASX:CYM)
Page 7
2024 Cyprium sequential leach testing:
Further drilling was conducted by Cyprium via 24 sonic drill holes across pads 3 to 6. Pulps from 18 of
these holes were composited and submitted for sequential leach in 2024. The resultant data set provided
calculated recoveries that supported the Metals X data set, with a mean of 50.3% and a standard
deviation of 7.6% (refer Figure 5).
Figure 5 – Heap Leach Recovery Distribution Curve (Cyprium Data)
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
Modifying Factors
Clause 20 of the JORC (2012) Code requires that all reports of Mineral Resources must have reasonable
prospects for eventual economic extraction, regardless of the classification of the resource. The Nifty
heap leach resource passes the RPEEE hurdle on the basis that the material has already been extracted
and stockpiled, and successfully processed in the past. The August 2024 MRE has established the
presence of contained copper available for leaching and recovery.
The infrastructure required for processing is present and ready for refurbishment, including the solvent
extraction plant and the electrowinning plant. The eastern end of the heap leach pad occurs within and on
top of the subsidence zone boundary, however, the subsidence zone is not considered to have
compromised the heap leach.
A mining study is not applicable, and metallurgical test work has been completed.
Cyprium Metals (ASX:CYM)
Page 8
Heap Leach MRE Report
Cyprium Metals Ltd
.
Heap Leach MRE
Nifty Project; Western Australia
Cyprium Metals Ltd
August 2024
Heap Leach MRE Report
Cyprium Metals Ltd
1
EXECUTIVE SUMMARY
MEC Mining (MEC) was commissioned by Cyprium Metals Limited (Cyprium) in April
of 2024 to complete a JORC 2012 compliant Mineral Resource estimation (MRE) report
for the Nifty Heap Leach Project. Indicated and Inferred Mineral Resources are shown
in Table 1-1. The grade tonnage curve is shown in Figure 1-1. These figures exclude
mineralised waste that is not compliant with JORC 2012 MRE reporting as discussed in
Section 17.
Table 1-1: MEC August 2024 Nifty Heap Leach Mineral Resource Estimate by Resource
Category at a zero Cu ppm cutoff grade, no top-cut applied
Resource
Category
Indicated
Inferred
Source
Volume (m3)
Density
(t/m3)
Tonnes (t)
Cu
(ppm)
Cu tonnes
(t)
% Metal
Stockpile
from drilling
6,253,350
1.70
10,636,950
4,100
43,580
80.6%
1,198,330
1.70
2,038,350
5,140
10,470
19.4%
54,050
TOTAL
7,451,680
1.70
12,675,300
4,260
100.00
MRE are reported above a zero Cu ppm economic cutoff with no top-cut. Mineral Resources are rounded to
reflect they are an estimation, numbers may not sum due to rounding. Excludes mineralised waste.
Figure 1-1: Grade tonnage curve MEC August 2024 heap leach MRE, Indicated and Inferred
Mineral Resources
271016 MEC Cyprium Metals Heap Leach MRE Report August 2024.docx
Nifty Heap Leach Project Page 2 of 74
Heap Leach MRE Report
Cyprium Metals Ltd
TABLE OF CONTENTS
1
2
EXECUTIVE SUMMARY ................................................................................................................................... 2
INTRODUCTION .............................................................................................................................................. 6
2.1
2.2
3
4
5
6
7
8
STATEMENT OF COMPETENCE....................................................................................................................... 6
FEES .............................................................................................................................................................. 7
INDEPENDENCE .............................................................................................................................................. 7
LOCATION ...................................................................................................................................................... 7
TENEMENTS ................................................................................................................................................... 8
HEAP LEACH OPERATIONS HISTORY .............................................................................................................. 9
8.1
9
10
SCOPE OF WORK................................................................................................................................. 6
ABOUT MEC MINING .......................................................................................................................... 6
Remaining Contained Copper........................................................................................................... 11
SITE VISIT...................................................................................................................................................... 11
DATABASE .................................................................................................................................................... 14
10.1 Overview .......................................................................................................................................... 14
10.2 Collar Data ........................................................................................................................................ 16
10.3 Topographical survey elevations compared to drillhole collar elevations ....................................... 17
10.4 Stockpile base elevation estimate .................................................................................................... 17
10.5 Downhole surveys ............................................................................................................................ 18
10.6 Sampling ........................................................................................................................................... 18
10.7 Assay Data ........................................................................................................................................ 19
10.8 Lithology Data .................................................................................................................................. 20
10.9 Density Data ..................................................................................................................................... 20
10.10 Drillholes excluded from the MRE .................................................................................................... 22
11
QAQC ........................................................................................................................................................... 23
11.1
11.2
11.3
11.4
11.5
11.6
12
Sample recovery ............................................................................................................................... 23
Assay precision ................................................................................................................................. 24
Standard results ............................................................................................................................... 24
Blank results ..................................................................................................................................... 26
Duplicate results ............................................................................................................................... 26
Assay bias ......................................................................................................................................... 26
MINERAL RESOURCE ESTIMATION............................................................................................................... 29
12.1 Methodology .................................................................................................................................... 29
12.2 Composite samples .......................................................................................................................... 29
12.3 Ore Block model ............................................................................................................................... 30
12.4 Grade estimation .............................................................................................................................. 31
12.5 Bulk density ...................................................................................................................................... 33
12.6 Geostatistics ..................................................................................................................................... 33
12.7 Classification..................................................................................................................................... 33
12.8 Validation ......................................................................................................................................... 35
12.9 Reasonable prospects hurdle ........................................................................................................... 38
12.10 Reported Mineral Resource ............................................................................................................. 38
13
14
COMPARISON WITH PREVIOUS MINERAL RESOURCE ESTIMATE ................................................................ 40
HEAP LEACH STOCKPILE ............................................................................................................................... 42
271016 MEC Cyprium Metals Heap Leach MRE Report August 2024.docx
Nifty Heap Leach Project Page 3 of 74
Heap Leach MRE Report
Cyprium Metals Ltd
15
METALLURGICAL TESTWORK RESULTS ........................................................................................................ 42
15.1 RMD Stem 3m Pilot Trial .................................................................................................................. 42
15.2 Metals X Sequential Leach Analysis.................................................................................................. 43
15.3 2024 Cyprium Sequential Leach Analysis ......................................................................................... 44
16
17
18
RISK ASSESSMENT ........................................................................................................................................ 45
CONCLUSIONS .............................................................................................................................................. 48
RECOMMENDATIONS .................................................................................................................................. 48
18.1
18.2
19
20
21
22
23
24
25
Survey ............................................................................................................................................... 48
Density.............................................................................................................................................. 48
DISCLAIMER ................................................................................................................................................. 49
ACKNOWLEDGEMENTS ................................................................................................................................ 49
COMPETENT PERSONS STATEMENT ............................................................................................................ 50
REFERENCES ................................................................................................................................................. 51
APPENDIX 1: JORC CODE TABLE 1 ................................................................................................................ 52
APPENDIX 2: SHEWHART PLOTS OF STANDARD RESULTS ........................................................................... 68
APPENDIX 3: GLOSSARY ............................................................................................................................... 70
LIST OF TABLES
Table 1-1: MEC August 2024 Nifty Heap Leach Mineral Resource Estimate by Resource Category at a zero Cu
ppm cutoff grade, no top-cut applied .................................................................................................................... 2
Table 8-1: Estimates of remaining contained Cu on heap leach stockpiles.......................................................... 11
Table 10-1: Number of drillholes, metres drilled and number of samples by drilling phase (not all drillholes
included in MRE) ................................................................................................................................................... 16
Table 10-2: Statistics on elevation difference between collar and heap leach surface ....................................... 17
Table 10-3: Sample length statistics across all drilling programs ......................................................................... 18
Table 11-1: Summary of standards used across 2014 RC and 2021 sonic drilling programs................................ 25
Table 12-1: Composite and raw sample statistics ................................................................................................ 29
Table 12-2: August 2024 OBM extents ................................................................................................................. 30
Table 12-3: Block model field attributes .............................................................................................................. 30
Table 12-4: Neighbourhood search parameters for August 2024 heap leach MRE ............................................. 32
Table 12-5: Percentage of block estimated at each estimation pass ................................................................... 33
Table 12-6: Comparison of raw, composite and block grade statistics for Cu (ppm) ........................................... 36
Table 12-7: MEC August 2024 Nifty Heap Leach Mineral Resource Estimate by Resource Category at a zero Cu
ppm cutoff grade, no top-cut applied .................................................................................................................. 39
Table 12-8: Comparison of August 2024 heap leach Mineral Resource Estimates for Indicated and Inferred
material only, at zero cutoff Cu ppm ..................................................................................................