MARCH 2026 QUARTERLY ACTIVITIES REPORT
HIGHLIGHTS
• Phase 1 Cathode Restart project progressing to plan, with:
- Significant work on site infrastructure completed in quarter
- Turnover and pre-commissioning of heaps underway
- SXEW plant construction at 50% of labour hours complete
- All significant capital items and first fills committed and in delivery
- Continued progress around regulatory sign-off on acid handling areas
• Commencement of copper cathode production expected in September Quarter 2026
• Key strategic hires to support copper production and exploration
- Justin de Mellion as Nifty Site General Manager
- Richard Holmes as Chief Development Officer (post quarter end)
- Exploration team growth to support increased activities
• Continued advancement of technical work supporting near-term growth at Nifty Copper
Complex through a new open-pit mine that recovers remaining oxides for cathode production
and accesses the large sulphide reserve below
• Review of exploration data identified numerous high-priority targets including Rainbow,
Stirling, NL04b and MB01 and significant un-assayed core
• Diamond drilling completed at Rainbow to extend known copper mineralisation, with assay
results expected in the June Quarter
• A$41 million equity capital raising to accelerate exploration and fund growth initiatives
• Cyprium well-funded to advance all key workstreams: A$96.5M cash at quarter-end
• Heightened focus on supply chain
- All major procured (but not delivered) items on construction plan being expedited
- Up to five months of sulphuric acid on the ground with current CYM suppliers
- Current diesel inventory supports three months of operations
2
ASX: CYM |
Cyprium Metals Limited (ASX: CYM / OTCQB: CYPMF) (Cyprium or the Company), a copper developer
focused on the phased restart of the Nifty Copper Complex in the Paterson region of Western Australia
(Nifty), is pleased to report its quarterly activities for the period ended 31 March 2026 (March Quarter).
Commenting on the March 2026 Quarter, Cyprium Executive Chairman Matt Fifield, said:
“Another significant quarter for Cyprium, with substantial progress on our Phase 1 Copper Cathode
Restart project and our future growth ambitions. The Cyprium team, together with our execution
partners, Macmahon and DECMIL, is delivering safely against our plan despite the challenging conditions
that have emerged for supply chains during the quarter.
The March 2026 quarter saw a tremendous team effort on the ground. Our operations team worked
seamlessly alongside our key technical partners to rapidly advance physical site readiness and planning
for operations later this year.
The emerging conflict in the Middle East has made our world more complex. In the quarter our integrated
project delivery team stepped up, working to ensure availability of all major procured items and first fills
that support our construction and commissioning activities. We secured multiple months of physical
supply of sulphuric acid and diesel either on site or within our supply chain to support near-term cathode
production.
Beyond our restart of cathode operations, we have continued to progress our technical work to expand
the Nifty Copper Complex beyond our Phase 1 restart. We look forward to updating shareholders and
outlining a staged approach to open-pit mining and growth in copper production.
In our broader portfolio we have a significant opportunity to unlock broader resource growth across our
extensive asset base in the Paterson Province. A first-pass review of historical data has identified several
compelling exploration targets that warrant further investigation.
We are excited about the Rainbow prospect – it stands out with large-scale geochemical anomalies
comparable to Nifty and is located near our operating base, just 30km to the north-northwest. There’s
strong potential for Rainbow and other targets to deliver additional oxide and sulphide feed within
trucking distance to Nifty’s processing facilities to support our future growth ambitions. We are delighted
that Richard Holmes has recently joined Cyprium as Chief Development Officer to lead exploration
strategy and development efforts across these assets.
Early in the quarter we completed a A$41 million capital raise in the quarter to support these growth
initiatives. Thank you to our new and existing shareholders for their support.
In summary, we are on mission. Our staged development approach is being executed. Cyprium is
emerging as a producer, and our team remains focused on building Australia’s next great copper
company.”
3
ASX: CYM |
PHASE 1 COPPER CATHODE RESTART PROJECT
During the March Quarter, Cyprium materially advanced the Phase 1 Copper Cathode Restart project
through construction activities at the Nifty Copper Complex.
Leach pads and heap leach support infrastructure
• De-silting and relining of
W-drains and ponds
Removal of sediment build-up and
reprofiling of all ponds and drainage
systems completed, with relining works
well progressed
W-Drains relined
Acid storage and distribution terminal
Pit dewatering pump
• Installation of leach
solution transport
infrastructure
Materially progressed, including
reinstallation of solution pipes across
the system and installation of new
pumps, cable trays and flow meters
• Heap turnover and
dripper line installation
Commenced physical turnover of
heaps and installed dripper lines
• Acid storage and
distribution terminal
Construction of the new acid storage
and distribution terminal, with dry
commissioning imminent
• Acid infrastructure sign-
off
Progress around regulatory sign-off as
works complete on acid handling areas
• Pit dewatering
infrastructure
Dewatering infrastructure installed
allowing water from the pit to be
pumped into the pond system and
blended with intermediate liquor for
leaching operations
Operational Readiness
• Operating procedures
and training
Operational readiness was a key focus
during the quarter. Development of
operating systems and processes
progressed meaningfully and is on
track to support heap leach and plant
commissioning and operations
• First fills First fill procurement underway with
committed delivery schedules
4
ASX: CYM |
Site infrastructure
• Camp facilities and
amenities
Significant refurbishment of camp
mess and rooms on site to
accommodate construction, drilling
and operational activities
SXEW Plant Refurbishment
• Refurbishment of Train B
of the existing SX-EW
plant
• Controls and
instrumentation for the
entire SX-EW plant
As at mid-April 2026, approximately
50% of planned labour hours for the
refurbishment works have now been
completed.
Works undertaken in the quarter
included:
• Concrete repairs and acid proof
coating works
• Installation of the Spintek filter
tanks and reagent bund tanks
• Reinstatement of pipework
throughout the system
• Installation of valves and gaskets
• Preparation for the installation of
new pumps and motors
• Replacement of cable trays and
installation of new cables
• Fiberglass repairs for the
refurbishment of the electro-
winning cells
• Refurbishment of the overhead
gantry crane supports and
installation of new busbar
• Cleaning of the cathode stripping
machine for refurbishment
All significant outstanding capital items
are committed and scheduled for
delivery.
Installation of Spintek filter tank
Reinstallation of piping to EW
Refurbishment of gantry crane supports
Timelapse videos of the Phase 1 Copper Cathode Restart project works during the quarter is available to
view on the Company’s website.
PROJECT OUTLOOK1
As noted above, the Phase 1 Copper Cathode Restart project has progressed materially. In the coming
quarter we expect continued execution across all phases of project construction, operational readiness,
supply chain build and pre-commissioning activities. Heap leach commissioning, plant practical completion
and commissioning, first cathode production and ramp up are expected to commence in the following
quarter.
1
Refer to important information on page 12 of this announcement regarding forward looking statements.
5
ASX: CYM |
ENERGY SECURITY AND SULPHURIC ACID SUPPLY
Across the quarter, Cyprium has been closely monitoring and proactively managing emerging risks from
potential supply chain disruptions that could arise from conflict in the Middle East or elsewhere.
Focus on securing Natural Gas, Diesel and Aviation Fuel and understanding exposure to availability
• Nifty Copper Complex is powered by natural gas. Primary site power is generated by natural gas
turbines that are fed by APA Group’s Pilbara Pipeline System. Natural gas is sourced through brokers
on the spot market from domestic gas production. At this time, Cyprium does not believe there is
any material impact on natural gas availability to site.
• Phase 1 Cathode Restart diesel fuel usage is relatively low. Our current and projected diesel
usage from construction activities and cathode operations is expected to be low. Our Phase 1
Cathode Restart is a re-leach of existing heap leach pads, which entails minimal material movement
particularly when compared to conventional mining operations. At this time, Cyprium holds multiple
months of projected diesel fuel usage on site.
• The remote location of the Nifty Copper Complex creates reliance on third-party access to fuel
to deliver people and supplies. Cyprium currently has one round-trip charter air service per week
to facilitate site access and regularly uses charter flights contracted by nearby mining operations.
Similarly, Nifty receives supplies by truck from Port Hedland and points across Australia. As a part
of managing potential exposure to disruption in fuel supply, management has discussed fuel
availability with our key suppliers. At this time, Cyprium believes that this secondary exposure does
not present a material business risk and continues to monitor the situation.
Focus on securing Sulphuric Acid supply chain
Events in the Middle East have placed unprecedented stress on the global supply of sulphur, and this has
had a cascading effect on the sulphuric acid market. These two markets have loose correlation but are in
fact two separate markets with limited crossover in customer base.
Sulphur is predominately supplied by refiners and petrochemical producers to global consumers that burn
the physical sulphur to generate sulphuric acid and power. Sulphur is non-reactive and therefore can be
transported over long distances without special equipment.
Sulphuric acid is predominately supplied by metal smelters and a smaller cohort of refiners and
petrochemical producers, is considered a hazardous material, and is transported using specialised
equipment.
Phase 1 Cathode Restart operations requires sulphuric acid to leach copper from oxide ores as a part of the
heap leach recovery process. There is no substitute. Cyprium has engaged with local logistics partners to
procure, store and transport sulphuric acid from their terminals to site. This is a specialised business and
our counterparty is one of the largest handlers of sulphuric acid in Australia. As of April, our supplier has up
to five months of Cyprium’s acid requirements in their terminals awaiting delivery to site. We understand that
the majority of our supplier’s acid is sourced from Australian and the Indo Pacific under long duration
arrangements, and that our supplier does not anticipate any disruption to supply.
Management continues to monitor the sulphuric acid market closely. At this time, we do not believe that
physical availability of sulphuric acid will present a material risk to our business plan or growth ambitions.
6
ASX: CYM |
GROWTH ACTIVITIES
PHASE 2 CATHODE PRODUCTION2
In parallel to the current Phase 1 Copper Cathode Restart project, Cyprium is advancing its evaluation of
opportunities to expand cathode production. The Phase 2 Cathode Production project seeks to further
leverage infrastructure that is being refurbished in Stage 1 to rapidly increase cathode production capacity.3
Nifty SX-EW plant, process trains and shared components4
The existing Nifty SX-EW plant comprises two independent process trains and additional shared components
servicing both process trains – “A Train” and “B Train” – and shared control systems as shown below.
• The Nifty SXEW Plant was built over time in a series of expansions until it reached its maximum
productive capacity of 25,000 tonnes
• The “B Train”, which Cyprium is currently bringing online, involves the newest areas of the plant,
including three mixer settlers, 42 EW cells, and many of the core components and instrumentation
required to run the entire plant
• Given Cyprium’s investment to re-establish the core components, expansion of productive capacity
would mainly entail refurbishment of additional cells and mixer settlers in the older and larger “A
Train”
As a part of the larger site-wide operational strategy, Cyprium is evaluating the potential for additional oxide
ore sources, including the shallow oxide material in the open pit identified in the Nifty Copper Complex PFS
(PFS) additional low-grade oxide ore stockpiles identified at site, as well as the potential to recover copper
from the existing pads at a higher rate. Each of these potential new sources would require an expanded
capacity in the Nifty SXEW, and newly mined oxide ore would likely require the construction of a new pad 7
for leaching operations.5
2
Refer to important information on page 12 of this announcement regarding forward looking statements.
3
The existing SX-EW plant at Nifty historically produced at a peak annual production rate of 25,000 tpa.
4
This figure shows preliminary drawings that are subject to change. Productive capacity is an estimate of the potential to produce at an
annualised volume and not a forecast.
5
Refer to the PFS, a copy of which was released to the ASX announcements platform by the Company announcement “Nifty PFS Confirms
$1,129m Pre-Tax NPV and 797kt Ore Reserve” dated 27 November 2024, for more information.
7
ASX: CYM |
Near surface oxides and additional low-grade stockpiles have potential to support
additional cathode production capacity6
Activity during the quarter focused on:
• Ongoing evaluation of oxide material in pit and additional low-grade stockpile material to improve
geological confidence;
• Mine planning work `to accelerate potential to access in-pit oxide ores; and
• Capital and operating cost estimates for mining the shallow in-pit oxide ore, construction of a new pad
7 and extending refurbishment of the SX-EW plant to A Train.
OPEN-PIT CONCENTRATE PRODUCTION7
Following on from the outcomes of the PFS, Cyprium continues to advance its evaluation of re-starting
concentrate production from the establishment of a new expanded surface mine at the Nifty Copper Complex
and refurbishment of the 50,000 tpa copper-in-concentrate flotation circuit and 2.8Mtpa mill on site.
During the quarter, management continued to refine and mature PFS outcomes, focusing on:
• Mine planning necessary to identify opportunities to accelerate production and de-risk potential for
interactions between the open pit and the abandoned underground mine workings;
• Evaluating the benefits of commencing concentrate production with the existing milling capacity, rather
than expanding the mill as contemplated in the PFS;
• Evaluating options to maximise utilisation of the large flotation circuit;
• Matching expanded processing capacity in the future to support the potential for additional ore feed
from Cyprium’s exploration interests at Rainbow and Maroochydore;
• Scope development and detailed costing for the refurbishment of the mill and the flotation plant; and
• Strategic review of existing regulatory approvals and mine closure plans, and identification of supporting
activity required to support concentrate production.
6
This figure shows preliminary drawings that are subject to change. Productive capacity is an estimate of the potential to produce at an
annualised volume and not a forecast.
7
Refer to important information on page 12 of this announcement regarding forward looking statements.
8
ASX: CYM |
EXPLORATION
NEAR NIFTY EXPLORATION
During the quarter, Cyprium completed RC and diamond drilling programs designed to test offset segments
of the Nifty host sequence. The programs comprised twelve RC holes for 2,806 metres and two diamond
holes for 1,751 metres.
Structural data obtained from diamond drill core confirmed Cyprium’s model that the Nifty host sequence
has been offset by post-mineral movement along discrete structures. As a result, historic drilling may not
have fully evaluated the potential for along-strike extensions to the Nifty deposit. The second diamond hole,
located 1.7 kilometres southeast of the Nifty pit, intersected traces of chalcopyrite as blebs and veinlets in
and around thin (sub-centimetre) bands of carbonate within the shale sequence, which indicates that the
mineralised system continues along strike to the southeast.
Future work will aim to locate thicker intervals of the prospective carbonate host rocks in these offset
segments.
Also during the quarter, a program of RC drilling commenced to test parts of the waste dump containing
visible copper oxide mineralisation.
PATERSON
Review of regional data
During the March Quarter, Cyprium completed a high-level first pass review of exploration data received
from IGO. The database for the Paterson region comprises more than 9,100 drill holes. In addition, the
database includes approximately 30,000 soil samples and extensive regional geophysical datasets, including
airborne magnetics, airborne and ground electromagnetic surveys, and ground gravity data.
Of note, much of the regional data was collected during the 1980s and 1990s when exploration efforts were
primarily directed toward materially higher-grade deposits. Cyprium is re-evaluating historic exploration
results to identify occurrences where mineralised grades may not have been considered significant at the
time but may represent potentially economic deposits under current market and operating conditions.
Cyprium’s assessment of both historic and recent datasets has identified several prospective target areas
with strong indicators of copper and associated mineralisation warranting further investigation. This includes
drill planning activities for high-priority targets already defined at the Rainbow and Rainbow South prospects.
RAINBOW
Diamond drilling program at Rainbow
A confirmatory diamond drill program of eight holes for 1,168.8 metres was completed at the Rainbow
Prospect during the quarter. Drilling tested the WMC +100ppm Cu lag anomaly over a strike length of 1.2
kilometres in an area where historic holes returned significant Cu-Ag intercepts (refer to ASX announcement
20 January 2026 for details). Many of the holes were designed to twin legacy RC holes and older data.
Cyprium drill hole locations are shown below.
9
ASX: CYM |
Rainbow drillhole locations
The drill core from the confirmatory drill program is being processed, with assay results expected in the
June Quarter.
MAROOCHYDORE
The Company continues to examine the potential for the Maroochydore Copper-Cobalt deposit to provide
additional ore feed to Nifty in a Paterson hub and spoke processing model. During the March Quarter,
Cyprium’s exploration team accelerated planning for the 2026 field season.
CUE COPPER-GOLD
Drilling was completed at the Heeler prospect in January 2026 to further test mineralisation identified in the
area in 2023. Anomalous mineralisation was intersected and is being interpreted to assist in designing follow
up work during 2026. Drilling was also completed at the Eelya South prospect in January 2026 to test for
eastern extensions of mineralisation tested in 2020, however, no significant mineralisation was intersected.
The Company continues to review its longer-term plans for the Cue Copper-Gold Project.
10
ASX: CYM |
CORPORATE
RECENT APPOINTMENTS
The Company has continued to build capability with targeted appointments during the quarter to support
execution of the Company’s strategy. Key appointments during the quarter included:
• Justin De Meillon – GM Nifty
• Additions to exploration team and finance and logistics staff to support emerging operations
Post quarter-end, the Company announced the appointment of Richard Holmes as Chief Development
Officer.8
INVESTOR SITE VISIT
In March, Cyprium hosted a group of institutional
investors at the Nifty Copper Complex. It was a fantastic
opportunity to show firsthand the progress of our Phase
1 Copper Cathode Restart project. We were proud to
showcase the site and the work our team has been
undertaking, with restart activities advancing rapidly.
REASEARCH COVERAGE INITIATED
Canaccord Genuity and Euroz Hartley recently initiated
research coverage of Cyprium.
Investor site tour at Nifty Copper Complex
8
Refer to the Company’s announcement titled “Executive Appointment” released to the ASX announcements platform on 30 April 2026.
11
ASX: CYM |
FINANCE UPDATE
CAPITAL RAISING AND ENTITLEMENT OFFER
During the quarter, Cyprium successfully completed a A$41 million (before costs) capital raising comprising
a A$36 million two-tranche Placement and a fully underwritten A$5 million Entitlement Offer at an issue price
of A$0.52 per share. The capital raising was successfully completed in March 2026.
CASH FLOWS FROM OPERATING ACTIVITIES
Net cash used in operating activities in the March Quarter of A$9.3m includes:
• A$4.6m for site operations and expenditure readying the site for future SXEW operation and cathode
production;
• A$1.1m salary expenses relating to Nifty on site costs and the Cyprium management team;
• A$1.7m on administration and corporate activities;
• A$2.2m on interest expense on borrowings; partially offset by
• A$0.5m of interest received on savings and term deposit accounts.
Payment of A$80,092 reported in item 6.1 of the attached Appendix 5B relates to payments to the Executive
Chairman and Non-Executive Directors (including superannuation)
CASH FLOWS FROM INVESTING ACTIVITIES
Net cash used in investing activities in the March Quarter of A$10.3m includes:
• A$8.2m net investment into property plant and equipment including capex works associated with the
restart of the Nifty Copper Complex; and
• A$2.2m net payments for exploration and evaluation including drilling programs at Nifty and near-
Nifty targets.
CASH FLOWS FROM FINANCING ACTIVITIES
Net cash provided from financing activities in the March Quarter of A$41.3m includes:
• A$41m proceeds via equity capital raise comprising a two-tranche Placement (A$36m) and a fully
underwritten Entitlement Offer (A$5m);
• A$2.4m proceeds through option conversions; partially offset by;
• A$2.0m transaction costs related to the issue of equity securities in the Placement and Entitlement
Offer.
CASH AND LIQUIDITY
As of the end of the March Quarter, the Company had A$96.5 million of cash on hand.
12
ASX: CYM |
This ASX announcement was authorised by the Cyprium Board.
For Enquiries:
Angus Miles | VP – Corporate Development and Investor Relations
+61 8 6374 1550
Chris Lim | External Media Relations Advisor
+61 493 392 001
communications@cypriummetals.com
Follow Cyprium Metals:
Subscribe to Email alerts https://cypriummetals.com/contact-us/subscribe-to-email-alerts/
LinkedIn https://www.linkedin.com/company/cyprium-metals/
X https://x.com/CypriumMetals
IMPORTANT INFORMATION - FORWARD LOOKING STATEMENTS
This document contains certain forward-looking statements and comments about future events, including in relation to Cyprium’s business,
plans and strategies, and expected events and trends in the industry in which Cyprium operates. Forward-looking statements can generally
be identified by the use of words such as “anticipate”, “believe”, “could”, “estimate”, “expect”, “forecast”, “intend”, “likely”, “may”, “outlook”,
“plan”, “predict”, “propose”, “should”, “target”, and “will”, and other similar expressions. Indications of, and guidance and outlook commentary
regarding, future earnings, financial performance and operating performance are also forward-looking statements.
Readers are cautioned not to place undue reliance on forward-looking statements. Forward-looking statements involve inherent risks,
assumptions and uncertainties, both general and specific, and there is a risk that forward-looking statements will not be achieved. A number
of important factors may result in Cyprium’s actual results and performance differing (including materially) from the plans, objectives, estimates,
targets and intentions expressed in forward-looking statements, and many of these factors are beyond the control of Cyprium, its directors
and management.
Statements or assumptions in this document may prove to be incorrect, and circumstances may change, and the contents of this document
may become outdated as a result. This may include statements about market and industry trends which are based on subjective interpretations
of prevailing market conditions.
Forward-looking statements in this document are based on Cyprium’s good faith assumptions as to the financial, market, regulatory and other
relevant conditions that will exist and affect Cyprium’s business and operations in the future. Cyprium does not give any assurance that these
assumptions will prove to be correct. There could be other factors that may cause actual results, conditions or events not to be as anticipated,
many of which are beyond Cyprium’s reasonable control.
Forward-looking statements in this document speak only as at the date of this document and, expect where required by applicable law,
Cyprium does not intend to update or revise any forward-looking statements, nor to publish forward-looking statements in the future, regardless
of whether new information, future events or other factors affect the information contained in this document.
Nothing in this document is, or is intended to be, a promise or representation as to the future, and past performance is not a guarantee of
future performance. None of Cyprium, its directors or management make any representation or warranty as to the accuracy of any forward-
looking statements in this document.
13
ASX: CYM |
APPENDIX A
ANNOUNCEMENTS IN THE MARCH 2026 QUARTER
Shareholders are encouraged to visit cypriummetals.com/investor-centre for comprehensive information on
announcements made during the March 2026 Quarter. This Quarterly Activities Report summarises key
updates extracted from ASX market announcements, which have been prepared in accordance with the
2012 edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources, and Ore
Reserves (JORC Code, 2012). For additional details, including JORC Code reporting tables where relevant,
please refer to the ASX announcements listed within this report.
Date Announcement
09/01/2026 Notification regarding unquoted securities - CYM
14/01/2026 Change of Director's Interest Notice
14/01/2026 Change of Director's Interest Notice
14/01/2026 Change of Director's Interest Notice
14/01/2026 Change of Director's Interest Notice
14/01/2026 Change of Director's Interest Notice
16/01/2026 Quarterly Activities/Appendix 5B Cash Flow Report
20/01/2026 Paterson Exploration Review Update
21/01/2026 Trading Halt
23/01/2026 A$41M Capital Raise via Placement & Entitlement Offer
23/01/2026 Capital Raise Presentation
23/01/2026 Proposed issue of securities – CYM
23/01/2026 Proposed issue of securities – CYM
23/01/2026 Cleansing Notice – Entitlement Offer
02/02/2026 Completion of Tranche 1 of the Placement
02/02/2026 Application for quotation of securities - CYM
02/02/2026 Cleansing Notice
03/02/2026 Application for quotation of securities – CYM
03/02/2026 Application for quotation of securities – CYM
03/02/2026 Cleansing Notice
04/02/2026 Becoming a substantial holder
04/02/2026 Investor Presentation
06/02/2026 Entitlement Offer – Offer Booklet and Access Letter
06/02/2026 Entitlement Offer – Notice to Ineligible Shareholders
06/02/2026 Notice of Extraordinary General Meeting/proxy Form
25/02/2026 Application for quotation of securities – CYM
25/02/2026 Cleansing Notice
05/03/2026 Results of Entitlement Offer
06/03/2026 Application for quotation of securities - CYM
06/03/2026 Change of Director’s Interest Notice
06/03/2026 S&P DJI Announces March 2026 Quarterly Rebalance
09/03/2026 Investor Presentation
09/03/2026 Results of Meeting
10/03/2026 Change in substantial holding
10/03/2026 Update - S&P DJI March 2026 Rebalance of the All Ordinaries
12/03/2026 Interim Financial Report
17/03/2026 Notification regarding unquoted securities - CYM
20/03/2026 Euroz Hartleys Conference Presentation
23/03/2026 Application for quotation of securities - CYM
23/03/2026 Completion of Tranche 2 of the Placement
23/03/2026 Cleansing Notice
23/03/2026 Change of Director's Interest Notice
23/03/2026 Change of Director's Interest Notice
23/03/2026 Change of Director's Interest Notice
23/03/2026 Change of Director's Interest Notice
23/03/2026 Change of Director's Interest Notice
14
ASX: CYM |
APPENDIX B
TENEMENT INFORMATION
Tenement Location Interest
Cyprium has a 100% interest in the Nifty Copper Complex, WA, which
comprises the following tenements:
M271SA, L45/74, L45/91, L45/102, L45/128, L45/143, L45/148, E45/6263,
M45/752, M45/753, M45/754 and P45/3177.
Paterson Province,
WA
100%
Cyprium has a 100% interest in the Maroochydore Copper Project, WA,
which comprises the following tenements:
E45/1840, E45/1841, E45/3011, E45/4318, E45/4319, M45/314, M45/315,
M45/317, M45/318, M45/492, M45/711, M45/712, M45/713, M45/745,
M45/746 and P45/3055.
Paterson Province,
WA
100%
Cyprium has a 100% interest in the Paterson Exploration Project, WA, which
comprises