JUNE 2024 QUARTERLY ACTIVITIES REPORT
Cyprium Metals is pleased to present its activities report for the quarter ended 30 June 2024.
Highlights included:
•
Release of Surface Mine Scoping Study (Scoping Study) shows economic potential of a
new surface mine at Nifty with NPV8% of $880 million and IRR of 46%1
•
Continued work on recommencement of operations at Nifty complex through Phase 1
restart of cathode production
•
Appointment of key senior executives Colin Mackey and Louis Chait to lead Cyprium’s
transition to operations
•
Appointment of Scott Perry to the Board to strengthen corporate governance and
board renewal
•
Advanced financing and offtake discussions to address near-term maturities and
forward capital requirements
•
Post-period end, entered commercial strategic partnership (Commercial Strategic
Partnership) with Glencore International AG (Glencore) for sale of copper products
from Nifty, significantly de-risking startup of Nifty’s two processing plants
•
$7.3 million of cash on hand and $12.5 million of total liquidity at end of quarter
“We continue to build momentum,” said Cyprium Executive Chair Matt Fifield. “In the March quarter,
we announced an updated Mineral Resource Estimate which outlined a million tonnes of copper in
resource at Nifty that could be fed through a refurbished and expanded concentrator. We also revealed
plans to advance to revenue quickly and cost-effectively by resuming cathode production while the
Company plans for the larger opportunity, the Nifty surface mine.”
“This quarter, with the release of our Scoping Study, we showcased the potential value to shareholders
that is created by building a new surface mine to feed a refurbished and expanded concentrator at
Nifty. We enhanced our ability to execute these plans by adding senior appointments at the executive
and board levels and post-period end, we attracted a top-tier customer and commercial ally in
Glencore. With regards to Phase 1, we advanced our mine planning and operational workstreams, as
well as our commercial discussions to raise the required funding to move forward. In short, we have
been driving Cyprium to become a near-term source of Australian copper. This important work
completed in the second quarter is the foundation for continued execution through the balance of the
year.”
Assumed copper price of AUD 13,000 using contract mining model. Refer to ASX announcement “Nifty Scoping Study
Demonstrates Economic Viability of Large Surface Mine” dated 23 May 2024.
1
ABN 48 002 678 640
T +61 8 6374 1550
ASX: CYM
Level 1, 437 Roberts Road
Subiaco, WA, 6008
www.cypriummetals.com
Surface Mine Scoping Study Released
During the quarter, Cyprium released the Scoping Study confirming the economic viability of
constructing a new surface mine to feed a refurbished and expanded concentrator at Nifty. The study
builds off the updated Mineral Resource Estimate which outlined one million tonnes of contained metal
released in March 2024:
Table 1 – Nifty Copper Deposit March 2024 Mineral Resource Estimate above 0.25% Cu
Figure 1 – Wireframe of the Nifty Mineral Resource with the LSM pit shell
The scoped operation envisions the construction of a new surface mine that feeds the existing
concentrator. The new mine targets the large sulphide resource area that extends down dip from the
previous excavations. Three 600-tonne excavators would feed approximately 4.5 million tonnes of ore
into the concentrator as expanded and refurbished. Projected average annual production would be
36,000 tonnes of copper in concentrate, or approximately 120,000 tonnes of concentrates, across a
17-year project life. Total expected life of mine metal recovery is 570,000 tonnes.
The study revealed a project with an NPV8 of $880m and an IRR of 46% on a capital expenditure of
A$175 million. This development takes advantage of existing infrastructure and positions Nifty as one
of the lowest near-term capital intensity copper projects globally. The Board has approved advancing
to a Pre-Feasibility Study to further refine and progress the project plan.
Cyprium Metals (ASX:CYM)
Page 2
Figure 2 – Cross Section of Optimisation Shells
Figure 3 – Plan View of Optimisation Shells including Heap Leach Area
Existing
Heap Leach Area
The Scoping Study was designed to optimise the new surface mine around economic access of the
sulphide ores that make up the vast majority of the Nifty orebody resources, without regard to any
other economic opportunities that exist on site.
The optimal pit shell from the Scoping Study confirmed that the required cutbacks to reach economic
cutoff in the new surface mine will eventually interact with the existing heap leach pads. This interaction
is shown on Figure 3 above.
Phase 1 Operations - Cathode Restart
Separate from the new surface mine activities, Cyprium has analysed the economic potential of
recovering remaining copper from the existing ore stockpiled on the heap leach pads and begun to
build a business case around this.
Nifty cathode operations ran under previous ownership from 1993 to 2009, producing ~220,000 tonnes
of cathode. Shutdown of the cathode operation occurred as the previous underground mine started
up and began producing concentrate. Previous management examined production and metallurgical
Cyprium Metals (ASX:CYM)
Page 3
accounting records to determine that the material stockpiled on the heap leach pads is approximately
17 million tonnes and contains an estimated 91,000 tonnes of unrecovered copper2. This remaining
copper has also been the subject of multiple studies aimed at recovering it including a feasibility study
in 2022 by previous management at Cyprium.
Last quarter, the Company developed plans to produce cathode by re-leaching the stockpiled
materials in place and processing the leachate through a refurbished processing plant. This was
deemed to be a low capital, low complexity plan to resume operations and generate initial cash flows.
In this quarter, the Company progressed technical and commercial work to higher confidence cost
estimation and operations planning.
Figure 4 – Stockpiled Material, ILS Pond, and Prior Cathodes Produced at Nifty
“We believe that an effective and low-cost program can recover approximately 6,000 tonnes of copper
per year following the refurbishment of the cathode plant, which we expect to be profitable business
at today’s copper prices” said Fifield. “As we will need to move this material eventually to access
deeper ore for the new surface mine, it makes sense to start this recovery process as soon as possible
to maximise return to shareholders.”
Across the quarter, the Company significantly advanced its understanding of the remaining resource,
and advanced its budgeting and estimation work necessary to refurbish the SX-EW plant, also referred
to as the cathode plant. Following an endorsement of the operational strategy by the Board, the team
began pre-operational planning and cost estimation work at a level required for eventual board
approval.
The Company looks forward to updating shareholders in this quarter as these plans reach a point of
sufficient certainty where disclosure is appropriate.
Senior Appointments at Executive and Board
In the quarter, the Company announced further key strategic appointments to the senior management
team. Colin Mackey joined Cyprium as Chief Operating Officer following a notable career at Rio Tinto
to lead operational execution. Louis Chait joined Cyprium as Chief Commercial Officer, bringing
extensive experience from his previous role as Chief Financial Officer – Copper at Glencore.
Scott Perry also joined the Board to continue the renewal of the Board and strengthen Cyprium’s
governance framework. Scott is the former CEO of Centerra Gold and took that company from a single
asset producer to a multi-asset operation with international market presence.
2
Note this is a non-JORC measure and to be treated with caution.
Cyprium Metals (ASX:CYM)
Page 4
Glencore Commercial Strategic Partnership
Following the quarter end, the Company announced a Commercial Strategic Partnership with
Glencore International AG. Elements of the partnership include advantageous sale terms for Nifty
copper products from its two processing plants, a sulphuric acid supply agreement, technical support,
and a $20 million working capital facility.
“The Commercial Strategic Partnership that we have entered into with Glencore is a significant step
in advancing our plans to recommence production,” said Fifield. “We have achieved favourable
commercial terms with Glencore who support our phased approach to redeveloping Nifty. These
terms derisk our startup plans significantly. We have a meaningful working capital facility that further
enhances our commercial relationship. Finally, Cyprium now has a strong and well-known customer
with sufficient contract duration and visible terms that support our many discussions with potential
funding partners.”
Financing Update
In the quarter, Cyprium engaged with multiple parties to determine the most actionable and costeffective paths to refinance near term maturities and fund forward capital needs. As of the time of this
announcement, the Company is evaluating multiple term sheets at every part of its capital structure.
We look forward to informing shareholders as these discussions conclude.
Exploration & Growth Projects
Last quarter, Cyprium announced a shallow high grade copper discovery at the Heeler Prospect near
Cue, approximately 10km southwest of the Company’s Hollandaire copper-gold deposit. During this
quarter, the Company followed up with additional diamond drilling. We look forward to updating
shareholders when appropriate.
Operating Expenses
Cyprium’s Nifty property is being maintained as an active mining site under its Western Australian
permits and in accordance with regulatory requirements. The maintenance of this status allow the
Company to move quickly into operations and results in higher expense levels than might occur under
a care and maintenance program.
Total operating expenses in the quarter included $1.9 million on site and Perth-based personnel and
$1.8 million on corporate costs including certain Nifty site costs. Investing activities were $1.9 million
on property, plant, and equipment and $0.4 million on exploration. Total operating expenses excluding
financing was $6.6 million in the quarter, down 30% from prior quarter.
Cyprium Metals (ASX:CYM)
Page 5
Cash and Liquidity
As of the end of the quarter, the Company had $7.3 million of cash on hand and $12.5 million of total
liquidity available to it given a full draw of remaining funds from its senior secured loan facility.
Following quarter end, the Company drew USD 3,500,000 in available funds under its secured loan
facility. Accordingly, as of the date of this announcement, the senior secured loan facility has a current
balance of $20.5 million and will mature in December 2024.
Cyprium also has an unsecured convertible note facility stemming from the original purchase of the
Paterson Copper projects with a face value of $36 million that is due in March 2025.
Payment of $132K reported in item 6.1 of the attached Appendix 5B relate to payments to Executive
Chair and Non-Executive Directors.
Capital Structure as of 30 June 2024
EXERCISE
PRICE
MATURITY
DATE
Performance Rights
Variable
Variable
81,092,228
Options
$0.06
31 Dec 24
423,860,979
Warrants
$0.048
30 June 25
SECURITY
Fully Paid Ordinary Shares
1,524,712,325
Total (Fully Diluted)
Convertible Notes (As Equity)
NUMBER
80,238,290
2,109,903,822
$0.3551
30 Mar 25
101,373,777
Announcements in Quarter
The Company encourage shareholders to find more information on cypriummetals.com/investorcentre. This Quarterly Activities Report contains information extracted from ASX market
announcements reported in accordance with the 2012 edition of the “Australasian Code for Reporting
of Exploration Results, Mineral Resources and Ore Reserves” (“JORC Code, 2012”). Further details
(including JORC Code reporting tables where applicable) of exploration results and technical
information referred to in this Quarterly Activities Report can be found in the following announcements
lodged on the ASX:
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
•
09 Apr 2024 Date of AGM and Closing Date for Director Nominations
18 Apr 2024 Board Appointment
18 Apr 2024 Initial Director’s Interest Notice
26 Apr 2024 Notice of Annual General Meeting/Proxy Form
26 Apr 2024 Annual General Meeting – Letter to Shareholders
30 Apr 2024 Quarterly Activities/Appendix 5B Cash Flow Report
02 May 2024 Shareholder Update Webinar Notification
09 May 2024 Investor Presentation
23 May 2024 Nifty Surface Mine Scoping Study
28 May 2024 Chairman’s Address – FY23 Annual General Meeting
28 May 2024 Annual General Meeting Presentation
30 May 2024 Change in Substantial Holding
06 Jun 2024 Senior Management Team Appointments
06 Jun 2024 Notification Regarding Unquoted Securities
26 Jun 2024 Change of Financial Year End
27 Jun 2024 Securities Trading Policy
28 Jun 2024 Change in Substantial Holding
Cyprium Metals (ASX:CYM)
Page 6
Tenement Information
Tenement
Location
Interest
Cyprium has an 80% joint venture interest in the Cue Copper-Gold project’s
copper, gold and silver mineralisation however Ramelius Resources Limited
(ASX Code: RMS) has a 100% interest in primary gold deposits that are not
associated with copper-gold deposits, for the following tenements at the Cue
Copper Project, WA:
L20/90, M20/225, M20/245, M20/277, M20/526, E20/606, E20/608, E20/616,
E20/629, E20/630, E20/659, E20/698, E20/700, E20/836 and P20/2279
Murchison
region, WA
80%
Cyprium has a 100% interest in the Nanadie Well Copper-Gold Project, WA,
which comprises the following tenements:
M51/887, E51/1040 and E51/1987
Murchison
region, WA
100%
Cyprium has a 100% interest in the Paterson Copper Project (Nifty Copper
Mine and Maroochydore Copper Project), WA, which comprises the
following tenements:
E45/1018, E45/1840, E45/1841, E45/3011, E45/4318, M45/314, M45/315,
M45/317, M45/318, M45/492, P45/2924, P45/2927, P45/3055, P45/3177,
P45/3150, P45/3151, L45/102, L45/128, L45/143, L45/148, L45/74, L45/91,
M271SA, E45/4319, E45/5705, E45/6263, M45/752, M45/753, M45/754,
M45/711, M45/712, M45/713, M45/745 and M45/746
Paterson
Province, WA
100%
Cyprium has a 100% interest in the Paterson Exploration Project, WA (IGO
earning up to 70%), which comprises the following tenements:
E45/1839, E45/2280, E45/2415, E45/2771, E45/2772, E45/2773, P45/2792,
P45/2793, P45/2794, P45/2801, P45/2802, P45/2803, P45/2804, P45/2805,
P45/2806, P45/2807, P45/2808, E45/3573, E45/3574, E45/3575, E45/3576,
E45/3577, E45/4151, E45/4205, E45/4234, E45/4862, E45/5199, E45/5300,
M45/1109, M45/1110, M45/1111, M45/1112, M45/1113 and M45/1114
Paterson
Province, WA
100%
Nanadie Well ELA51/1986 was withdrawn during the quarter. Aside of this, there were no
other changes in tenement holdings during the quarter.
Cyprium Metals (ASX:CYM)
Page 7
This ASX announcement was approved and authorised by the Board on Cyprium Metals Limited.
Further information:
Matt Fifield
Manu Trivedi
John Gardner
Executive Chair
matt.fifield@cypriummetals.com
Chief Financial Officer, Interim
manu.trivedi@cypriummetals.com
Investor and Media Relations
communications@cypriummetals.com
T +61 8 6374 1550
E communications@cypriummetals.com
About Cyprium Metals Limited
Cyprium Metals Limited (ASX: CYM) is an ASX-listed Australian copper company. Its flagship property is
the Nifty Copper Mine in Western Australia, which previously produced significant copper from both oxide
and sulphide resources. Cyprium is focused on redeveloping Nifty, which has the advantage of significant
invested capital, data from a long operating history, large-scale resources, current operational approvals,
and recent investment in the property.
The Company’s other assets include significant copper-focused properties in the Paterson and Murchison
Provinces, including multiple defined resources.
Visit www.cypriummetals.com for further information.
Competent Person Statement
The information in this announcement that relates to exploration results is based on and fairly represents
information compiled by Australian Institute of Geoscientists member Mark Styles. Mark is Exploration
Manager of Cyprium Metals Limited and holds shares in the Company. Mark has sufficient experience
relevant to the style of mineralisation and types of deposits under consideration and to the activities being
undertaken to qualify as a Competent Person as defined in the 2012 edition of the Australasian Code of
Reporting of Exploration Results, Mineral Resources and Ore Reserves. Mark consents to the inclusion in
this announcement of the matters based on his work in the form and context in which it appears.
The information in this report that relates to estimation and reporting of Mineral Resource Estimates is an
accurate representation of the available data and is based on information compiled by external consultants
and Mr. Peter van Luyt who is a member of the Australian Institute of Geoscientists (2582). Mr. van Luyt is
the General Manager – Geology and Exploration for Cyprium Metals Limited, in which he is also a
shareholder. Mr. van Luyt has sufficient experience which is relevant to the styles of mineralisation and
types of deposit under consideration and to the activity which he is undertaking to qualify as a Competent
Person (CP). Mr. van Luyt consents to the inclusion in the report of the matters based on his information in
the form and context in which it appears.
Cyprium confirms that it is not aware of any new information or data that materially affects the information
included in the original market announcements and, in the case of estimates of Mineral Resources, which
all material assumptions and technical parameters underpinning the estimates in the relevant market
announcement continue to apply and have not materially changed. The Company confirms that the form
and context in which the Competent Person’s findings are presented have not materially changed from the
original market announcement.
Cyprium Metals (ASX:CYM)
Page 8
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
Appendix 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
CYPRIUM METALS LIMITED
ABN
Quarter ended (“current quarter”)
48 002 678 640
30 JUNE 2024
Consolidated statement of cash flows
1
1.1
1.2
Current quarter
Year to date
$A’000
$A’000
1.3
1.4
1.5
1.6
1.7
1.8
Cash flows from operating activities
Receipts from customers
Payments for
(a) exploration & evaluation
(b) development
(c) production
(d) staff costs
(e) administration and corporate costs
Dividends received (see note 3)
Interest received
Interest and other costs of finance paid
Income taxes paid
Government grants and tax incentives
Other (provide details if material)
(1,764)
(1,879)
314
(510)
-
(3,176)
(4,496)
423
(2,457)
-
1.9
Net cash from / (used in) operating activities
(3,839)
(9,706)
(1,954)
(453)
-
(4,475)
(1,284)
-
2
Cash flows from investing activities
2.1
Payments to acquire or for:
(a) entities
(b) tenements
(c) property, plant and equipment
(d) exploration & evaluation
(e) investments
(f) other non-current assets
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 1
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
Consolidated statement of cash flows
2.2
2.3
2.4
2.5
Proceeds from the disposal of:
(a) entities
(b) tenements
(c) property, plant and equipment
(d) investments
(e) other non-current assets
Cash flows from loans to other entities
Dividends received (see note 3)
Other (provide details if material)
2.6
Net cash from / (used in) investing activities
3
3.5
3.6
3.7
3.8
3.9
3.1
Net cash from / (used in) financing activities
4
Net increase / (decrease) in cash and cash
equivalents for the period
3.2
3.3
3.4
4.1
4.2
4.3
4.4
Cash and cash equivalents at beginning of period
Net cash from / (used in) operating activities (item
1.9 above)
Net cash from / (used in) investing activities (item
2.6 above)
Net cash from / (used in) financing activities (item
3.10 above)
Consolidated statement of cash flows
4.5
4.6
Year to date
$A’000
94
-
164
-
(2,313)
(5,595)
-
-
-
-
-
-
-
-
-
-
(6,152)
(15,301)
13,463
22,591
(3,839)
(9,706)
(2,313)
(5,595)
-
-
Current quarter
Year to date
$A’000
$A’000
-
21
7,311
7,311
Cash flows from financing activities
Proceeds from issues of equity securities
(excluding convertible debt securities)
Proceeds from issue of convertible debt securities
Proceeds from exercise of options
Transaction costs related to issues of equity
securities or convertible debt securities
Proceeds from borrowings
Repayment of borrowings
Transaction costs related to loans and borrowings
Dividends paid
Other (provide details if material)
3.1
Current
$A’000
Effect of movement in exchange rates on cash
held
Cash and cash equivalents at end of period
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 2
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
5
Reconciliation of cash and cash equivalents
Current
quarter
Previous
quarter
at the end of the quarter (as shown in the consolidated
statement of cash flows) to the related items in the
accounts
$A’000
$A’000
5.1
Bank balances
4,547
247
5.2
Call deposits
2,764
13,216
5.3
Bank overdrafts
-
-
5.4
Other (provide details)
-
-
7,311
13,463
5.5
Cash and cash equivalents at end of quarter (should
equal item 4.6 above)
6
Payments to related parties of the entity and their associates
6.1
Aggregate amount of payments to related parties and their associates included
in item 1
132
6.2
Aggregate amount of payments to related parties and their associates included
in item 2
-
Current
quarter
$A'000
Note: if any amounts are shown in items 6.1 or 6.2, your quarterly activity report must include a
description of, and an explanation for, such payments.
7.
Financing facilities
Note: the term “facility’ includes all forms of financing
arrangements available to the entity.
Add notes as necessary for an understanding of the
sources of finance available to the entity.
7.1
Loan facilities
7.2
Total facility
amount at
quarterend
$A’000
Amount drawn at
quarter
end
$A’000
20,595
15,450
Credit standby arrangements
-
-
7.3
Other (please specify)
-
-
7.4
Total financing facilities
-
-
7.5
Unused financing facilities available at quarter end
7.6
Include in the box below a description of each facility above, including the lender, interest
rate, maturity date and whether it is secured or unsecured. If any additional financing
facilities have been entered into or are proposed to be entered into after quarter end,
include a note providing details of those facilities as well.
Investor:
Funded Amount:
Facility Term:
Coupon:
OID:
Security:
5,145
Nebari Natural Resources Credit Fund II, LP
Up to USD14.5 million, net of original issue discounts (OID)
Until 31 December 2024
Secured Overnight Financing Rate (SOFR)+6.5% p.a. paid monthly
5.0% on Tranche 1 and 10.0% on Tranche 2
Over the assets of Cyprium and its projects
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 3
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
8
Estimated cash available for future operating activities
$A’000
8.1
(3,839)
8.3
8.4
8.5
8.6
Net cash from / (used in) operating activities (item 1.9)
(Payments for exploration & evaluation classified as investing activities)
(item 2.1(d))
Total relevant outgoings (item 8.1 + item 8.2)
Cash and cash equivalents at quarter end (item 4.6)
Unused finance facilities available at quarter end (item 7.5)
Total available funding (item 8.4 + item 8.5)
8.7
Estimated quarters of funding available (item 8.6 divided by item 8.3)
8.2
(453)
(4,292)
7,311
5,145
12,456
2.9
Note: if the entity has reported positive relevant outgoings (ie a net cash inflow) in item 8.3, answer item 8.7 as “N/A”.
Otherwise, a figure for the estimated quarters of funding available must be included in item 8.7.
8.8
If item 8.7 is less than 2 quarters, please provide answers to the following questions:
8.8.1
Does the entity expect that it will continue to have the current level of net operating
cash flows for the time being and, if not, why not?
Answer: N/A
8.8.2
Has the entity taken any steps, or does it propose to take any steps, to raise further
cash to fund its operations and, if so, what are those steps and how likely does it
believe that they will be successful?
Answer: N/A
8.8.3
Does the entity expect to be able to continue its operations and to meet its business
objectives and, if so, on what basis?
Answer: N/A
Note: where item 8.7 is less than 2 quarters, all of questions 8.8.1, 8.8.2 and 8.8.3 above must be answered.
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 4
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
Compliance statement
1
This statement has been prepared in accordance with accounting standards and policies which
comply with Listing Rule 19.11A.
2
This statement gives a true and fair view of the matters disclosed.
Date:
31 JULY 2024
Authorised by: By the board
(Name of body or officer authorising release – see note 4)
Notes
1.
This quarterly cash flow report and the accompanying activity report provide a basis for informing the market about the
entity’s activities for the past quarter, how they have been financed and the effect this has had on its cash position. An
entity that wishes to disclose additional information over and above the minimum required under the Listing Rules is
encouraged to do so.
2.
If this quarterly cash flow report has been prepared in accordance with Australian Accounting Standards, the definitions
in, and provisions of, AASB 6: Exploration for and Evaluation of Mineral Resources and AASB 107: Statement of Cash
Flows apply to this report. If this quarterly cash flow report has been prepared in accordance with other accounting
standards agreed by ASX pursuant to Listing Rule 19.11A, the corresponding equivalent standards apply to this report.
3.
Dividends received may be classified either as cash flows from operating activities or cash flows from investing activities,
depending on the accounting policy of the entity.
4.
If this report has been authorised for release to the market by your board of directors, you can insert here: “By the board”.
If it has been authorised for release to the market by a committee of your board of directors, you can insert here: “By the
[name of board committee – eg Audit and Risk Committee]”. If it has been authorised for release to the market by a
disclosure committee, you can insert here: “By the Disclosure Committee”.
5.
If this report has been authorised for release to the market by your board of directors and you wish to hold yourself out as
complying with recommendation 4.2 of the ASX Corporate Governance Council’s Corporate Governance Principles and
Recommendations, the board should have received a declaration from its CEO and CFO that, in their opinion, the financial
records of the entity have been properly maintained, that this report complies with the appropriate accounting standards
and gives a true and fair view of the cash flows of the entity, and that their opinion has been formed on the basis of a
sound system of risk management and internal control which is operating effectively.
ASX Listing Rules Appendix 5B (17/07/20)