ASX ANNOUNCEMENT
12 September 2024
Updated Announcement and Retraction:
Re-optimisation of Nifty New Surface Mine significantly
reduces strip ratio
Cyprium Metals Limited (ASX: CYM) (Cyprium) refers to its earlier ASX release dated 9 September
2024 entitled “Re-optimisation of Nifty New Surface Mine significantly reduces strip ratio” (Earlier
Release).
Cyprium has consulted with the ASX and wishes to clarify that the pit optimisation update in the
Earlier Release is a study to examine changes in certain parameters and progress the PFS, and
accordingly, there are no changes to the original Scoping Study released on 23 May 2024 (Scoping
Study).
Whilst Cyprium considers that there will be a number of positive outcomes from the updated mine
optimisation, at this stage there are no formal changes to production target or any of the forecast
financial information in the Scoping Study.
Accordingly, Cyprium wishes to formally retract statements in the Earlier Release made which
suggested that there would be capital and operating cost reductions, an increase in the mine life or
better economics. Investors are advised not to make any investment decision on these statements.
Cyprium has amended Table 1 (front page of the Earlier Release) on the basis that further technical
and economic analysis is required to confirm that additional potential material from the re-optimised
pit design can be included as feed for the planned concentrator and cathode plant operations.
Accordingly, certain terminology has been updated with similar amendments made to MEC report.
Cyprium attaches an updated ASX release with the retracted statements removed.
This ASX announcement was approved by the Cyprium Board of Directors.
Further information:
Matt Fifield
John Gardner
Executive Chair
Investor and Media Relations
matt.fifield@cypriummetals.com
communications@cypriummetals.com
T +61 8 6374 1550
E communications@cypriummetals.com
ABN 48 002 678 640
T +61 8 6374 1550
ASX: CYM
Level 1, 437 Roberts Road
Subiaco, WA, 6008
www.cypriummetals.com
ASX ANNOUNCEMENT
12 September 2024
Re-optimisation of Nifty New Surface Mine significantly
reduces strip ratio
Cyprium Metals Limited (ASX: CYM) (Cyprium) is pleased to provide an update relating to its
previously released Scoping Study for the new surface mine at the Nifty copper complex. Cyprium’s
technical partner MEC Mining (MEC) completed an updated geotechnical study to advance
Cyprium’s knowledge of the expected mining conditions to a Pre-Feasibility level of confidence.
Following a peer review, this updated geotechnical information has now been incorporated in a new
mine optimisation as a part of the forthcoming Pre-Feasibility Study (PFS). The mine re-optimisation
has resulted in significantly more favourable strip ratios, and through reduction in footprint,
preserved the life of the existing cathode plant.
Highlights include:
•
Reduction in strip ratio by 25% to 7.3:1 from previous estimate of 9.7:1 in May 2024
Scoping Study, based on lower waste movements and the potential for additional
sulphide and transitional material to be concentrator feed
•
New pit shell preserves SXEW infrastructure over the expected life of heap leach
operations
•
Overall pit strip ratio of 6.3:1 when potential oxide, transitional and sulphide material
are taken into consideration
•
Updated Nifty new surface mine reserve expected in October 2024 with PFS to follow
“The updated mine optimisation is a material development for Cyprium and is a result of following a
thoughtful mine development sequence from end-to-end,” said Cyprium Executive Chair Matt Fifield.
“A number of expected positive outcomes: reduced footprint, and importantly the ability to continue
to generate revenue from the cathode plant throughout the life of the surface mine. We are
incorporating these wins into our restart planning and PFS work now.”
Table 1 – Updated Mine Optimisation Outcomes
Scoping Study Pit
Design
Optimisation Shell
Optimisation Shell
Concentrator Feed Only
Potential Sulphide &
Transitional
Potential Oxide,
Sulphide & Transitional
-
-
11.1
Sulphide & Transitional (Mt)
69.6
84.4
84.4
Total Waste (Mt)
675.2
614.2
603.1
Strip Ratio (W:O)
9.7
7.3
6.3
Oxide (Mt)
Note: All tonnages noted are rounded, figures are from block model optimisations and do not constitute reserves.
Optimisation shell figures are not designed or scheduled. This table displays material within the current Mineral
Resource Statement that reports to the optimised pit shell, and is not classified here as a JORC category of resource.
Qualifying Statement: This update demonstrates changes in projected strip ratios resulting from a re-optimised pit at
the new Nifty surface mine based solely on updated geotechnical information alone. All other inputs into the reABN 48 002 678 640
T +61 8 6374 1550
ASX: CYM
Level 1, 437 Roberts Road
Subiaco, WA, 6008
www.cypriummetals.com
optimisation were identical to the May 2024 Scoping Study (please refer to company announcements for additional
information). No changes in production rates, unit costs and/or macroeconomic assumptions were made between
the May 2024 Scoping Study and the results of the re-optimised pit presented in this report. As the work on the reoptimisation was only conducted to the point of determining material movements and strip ratios, the Company can
draw no conclusion as to the likely economic impact of the pit re-optimisation.
Figure 1 – High Level Total Material Movement Schedule
Geotechnical Update
In May 2024 Cyprium completed a Scoping Study that was optimised based on concentrate feed and
primarily focused on illustrating the size of the opportunity for the new Nifty Surface Mine.
The Scoping Study identified the requirement for geotechnical refinement (refer Section 5 of the
Cyprium’s ASX release 23 May 2024). The Scoping Study noted that “site work was completed in
January 2024 with final assessment and conclusions expected in the second half of 2024.” A final
assessment was completed by MEC in July 2024 and then independently reviewed in August 2024,
with the overarching recommendation that the new geotechnical data meets the requirements for a
Pre-feasibility Study.
MEC’s new geotechnical analysis involved reassessment of all historical geotechnical drilling and
testing data, along with the inclusion of six new holes drilled in 2023/2024. MEC examined overall rock
mass analysis, bench scale rock mass stability and bench face angles stability inclusive of major
structures. The resulting analysis has been incorporated into the technical parameters of the new Nifty
Surface Mine, resulting in material improvements to the pit optimization. Further details of the new
geotechnical work completed has been provided in MEC’s report that has been appended to this ASX
release.
“This new geotech information highlights the potential for material cost reduction by using steeper wall
angles that mirror the natural bedding planes of the shales that overlay the Nifty sulphide deposit,”
said Cyprium Chief Operating Officer Colin Mackey. “The smaller footprint lessens the total material
movements, increases the speed to both oxide and sulphide, and improves overall site interactions
and operational flexibility given the extended preservation of SX-EW infrastructure.”
Cyprium Metals (ASX:CYM)
Page 2
“One of the development sequencing trade-offs we have been thinking through in the background is
the interaction between the surface mine and the cathode plant,” said Fifield. “Previously, this meant
that while the cathode restart was low complexity and likely very profitable, it also had an uncertain life
depending on Cyprium’s ability to progress the new surface mine quickly. Now, the benefit of having
a refurbished cathode plant is available for a far longer time. We’re working through what that means
in terms of our overall business plan, but it is clear that it is positive.”
Figure 2 – Optimiser Pit Phases Cross-Section and Scoping Pit Design
Figure 3 - Comparison of Surface Mine and Heap Leach Interactions
Cyprium Metals (ASX:CYM)
Page 3
Next Steps
The new Nifty Surface Mine optimization is a key milestone that will cascade into the delivery of
important pieces of work for Cyprium.
Ore Reserve & Pre-Feasibility Study
An Ore Reserve is expected to be released in October 2024. This work is a part of the Prefeasibility
Study work underway that is focused on around the new surface mine at Nifty and the restart of the
existing concentrator.
Given the positive outcomes of the updated new surface mine optimisation, Cyprium is considering
the implications of being able to preserve the Cathode Plant infrastructure for significantly longer than
previously anticipated. Cyprium’s upcoming PFS will also assess potential of additional cathode
production from delivery of oxide from the new surface mine in conjunction with planned retreatment
of material on existing heap leach pads.
“Nifty’s sulphide resource remains Cyprium’s largest value driver,” said Fifield, “and the more we work
on it, the better it gets. We look forward to demonstrating the potential benefits of a lower strip ratio
and full utilisation of the cathode plant in our upcoming studies.”
“We are pleased about sharing these positive announcements – the team’s diligent work on restart
planning continues to improve the potential and speed to market,” said Fifield. “We look forward to
providing shareholders with additional information on our execution strategy in the near future.”
This ASX announcement was approved by the Cyprium Board of Directors.
Further information:
Matt Fifield
John Gardner
Executive Chair
Investor and Media Relations
matt.fifield@cypriummetals.com
communications@cypriummetals.com
T +61 8 6374 1550
E communications@cypriummetals.com
Cyprium Metals (ASX:CYM)
Page 4
Competent Person Statement
The information in this report that relates to the updated new Nifty surface mine optimisation is based on
information compiled by Christofer Catania, a Competent Person who is a Fellow of the Australasian
Institute of Mining and Metallurgy. Christofer Catania is employed by MEC Mining Group Pty Ltd as a
consultant for Cyprium Metals Ltd.
Christofer Catania has sufficient experience relevant to the style of mineralisation, type of deposit under
consideration and the activity being undertaken to qualify as a Competent Person as defined in the 2012
Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore
Reserves’. Christofer Catania consents to the inclusion in the report of the matters based on the
information in the form and context in which it appears.
Cyprium confirms that it is not aware of any new information or data that materially affects the information
included in the original market announcements and, in the case of estimates of Mineral Resources, which
all material assumptions and technical parameters underpinning the estimates in the relevant market
announcement continue to apply and have not materially changed. The Company confirms that the form
and context in which the Competent Person’s findings are presented have not materially changed from
the original market announcement.
About Cyprium Metals Limited
Cyprium Metals Limited (ASX: CYM) is an ASX-listed Australian copper company. Its flagship property is
the Nifty Copper Mine in Western Australia, which previously produced significant copper from both oxide
and sulphide resources. Cyprium is focused on redeveloping Nifty, which has the advantage of significant
invested capital, data from a long operating history, large-scale resources, current operational approvals,
and recent investment in the property.
The Company’s other assets include significant copper-focused properties in the Paterson and Murchison
Provinces, including multiple defined resources.
Visit www.cypriummetals.com for further information.
Cyprium Metals (ASX:CYM)
Page 5
Cyprium – Nifty Copper Operation
271019 – Pit Optimisation Update
Cyprium – Nifty Copper Operation
271019 – Pit Optimisation Update
September 2024
Cyprium – Nifty Copper Operation | Page 1 of 15
Cyprium – Nifty Copper Operation
271019 – Pit Optimisation Update
TABLE OF CONTENTS
STATEMENT OF COMPLIANCE ................................................................................................................................ 3
CAUTIONARY & DISCLAIMER .................................................................................................................................. 3
1
SCOPE & INTRODUCTION ............................................................................................................................... 4
2
INPUTS & ASSUMPTIONS ............................................................................................................................... 4
2.1
3.1
Geotechnical....................................................................................................................................... 5
Optimisation Results .......................................................................................................................... 7
3.1.1
3.1.2
3.2
4
Shell Generation ................................................................................................................... 7
Pit Phases ............................................................................................................................ 10
High Level Schedule .......................................................................................................................... 12
OUTCOMES & RECOMMENDATIONS ........................................................................................................... 13
4.1
Recommended Further Work ........................................................................................................... 14
TABLE OF FIGURES
Figure 1. Historical Geotechnical Data (MEC 271100 CYM Geotechnical PFS – final V1.0) .................................... 5
Figure 2. Geotechnical drill hole Locations (2023 drilling) (MEC 271100 CYM Geotechnical PFS – final V1.0) ...... 6
Figure 3. Summary overview of revised geotechnical zones and parameters. ...................................................... 7
Figure 4. Initial Optimisation Overview .................................................................................................................. 8
Figure 5. Optimisation pits long-section with Scoping study pit design. ................................................................ 8
Figure 6. Optimisation pits cross-section with Scoping study pit design. ............................................................... 9
Figure 7. Pit phases overview ............................................................................................................................... 10
Figure 8. Pit extents with Resource category overlay. ......................................................................................... 10
Figure 9. Optimiser pit phases long-section and Scoping pit design. ................................................................... 11
Figure 10. Optimiser pit phases cross-section and Scoping pit design. ................................................................ 11
Figure 11. Pit phase physicals ............................................................................................................................... 12
Figure 12. High level physicals per year. ............................................................................................................... 12
Figure 13. Pit phases versus Scoping pit with SXEW infrastructure. .................................................................... 13
TABLE OF TABLES
Table 1 MARCH 2024 MRE ...................................................................................................................................... 5
Table 2. Initial optimisation pit physicals. .............................................................................................................. 9
Table 3. Optimisation phase physicals.................................................................................................................. 13
REFFERENCES
Cyprium - MRE. (2024-c). Updated Nifty Mineral Resource Estimate Reaches 1 Million Tonnes Contained Copper.
Cyprium.
Cyprium – Nifty Copper Operation | Page 2 of 15
Cyprium – Nifty Copper Operation
271019 – Pit Optimisation Update
STATEMENT OF COMPLIANCE
The information in this report that relates to the Nifty Optimisation Study, and is based on information
compiled by Christofer Catania, a Competent Person who is a Fellow of the Australasian Institute of
Mining and Metallurgy. Christofer Catania is employed by MEC Mining Group Pty Ltd as a consultant
for Cyprium Metals Ltd.
Christofer Catania has sufficient experience relevant to the style of mineralisation, type of deposit
under consideration and the activity being undertaken to qualify as a Competent Person as defined in
the 2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and
Ore Reserves’. Christofer Catania consents to the inclusion in the report of the matters based on the
information in the form and context in which it appears.
Signed
____________________________________ 11th September 2024
Christofer Catania B.Eng(Mining) MBA FAusIMM 228366 GAICD
CAUTIONARY & DISCLAIMER
MEC have generated this summary report on pit optimisation works completed as part of ongoing study works.
The material contained is for the purpose of examining changes in parameters and does not constitute a scoping
or feasibility study, and estimated tonnages do not meet the requirements to be treated with the same
confidence levels of JORC code or Scoping study guidelines. Works contained are subject to change and review
during the reserves and pre-feasibility study works yet to be completed. All inclusions should be taken as
indicative and should not be relied upon for financial modelling or decision. MEC take no liability to use outside
the intended purpose and scope as defined in this document.
Cyprium – Nifty Copper Operation | Page 3 of 15
Cyprium – Nifty Copper Operation
271019 – Pit Optimisation Update
1
SCOPE & INTRODUCTION
MEC was engaged by Cyprium Metals (Cyprium) to complete an Ore Reserves Estimate and Pre-feasibility study
works for the new open pit planned for the Nifty copper complex (NCC), in Western Australia. These scopes
follow earlier work completed by MEC, namely the Mineral Resource Estimate (MRE) released in March 2024
and the Open Pit Scoping Study for NCC released in May 2024.
A recommendation from the May 2024 Scoping Study was for the client to commission a Pre-feasibility level
Geotechnical Engineering study that re-examined historical data and brought in additional geotechincal
information from new drill holes. MEC completed this Geotechnical Study in July 2024, demonstrating improved
pit slope parameters.
This Pit Optimisation Update study was completed as part of the ongoing study works, with the primary objective
in assessing the effects of the improved geotechnical modelling.
2
INPUTS & ASSUMPTIONS
The optimisation was completed using assumptions derived from the initial Scoping Study build up and results
released in June 2024, incorporating minor updates where subsequent study works had been advanced. No
material changes in assumptions were applied in this examination apart from the geotechnical parameters and
standard revenue ranging.
Assumptions included:
o
Geotechnical primary domains and “Special Zones” with associated overall slope angles
o
Rock types – inclusive of “Special Zones”
o
Mining cost inclusive of positional cost adjustment factors
o
Metallurgical recovery by rock type
o
Revenue
o
Processing costs by rock type
o
Selling Costs
o
Mining Loss and Dilution
o
Maximum process plant throughput
The geological model utilised in this optimisation is the Mineral Resource block model that was used for the NCC
Scoping study. This model was developed as part of the Mineral Resource Estimate March 2024, completed by
MEC Mining and released on the 14th of March 2024 (Cyprium - MRE, 2024-c). The MRE is summarised in Table
1.
Cyprium – Nifty Copper Operation | Page 4 of 15
Cyprium – Nifty Copper Operation
271019 – Pit Optimisation Update
Table 1 MARCH 2024 MRE
Measured
Indicated
Inferred
Total
OXIDISATION TYPE
Mt
%
Cu t
Mt
%
Cu t
Mt
%
Cu t
Mt
%
Cu t
OXIDE, SAP & TRANS
2.6
1.02%
26,471
17.52
0.74%
130,081
0.85
0.70%
5,902
21.0
0.77%
162,454
SULPHIDE
35.45
0.98%
347,610
63.4
0.80%
505,685
5.2
0.43%
22,479
104.1
0.84%
875,774
TOTAL
38.06
0.98%
374,081
80.91
0.79%
635,766
6.05
0.47%
28,381
125.0
0.83%
1,038,228
Numbers are rounded to reflect a suitable level of precision and may not sum
2.1
Geotechnical
MEC completed a Pre-feasibility level Geotechnical study as a recommendation from the Scoping study works.
This analysis reassessed all historical geotechnical drilling and testing data, along with inclusion of 6 new holes
drilled in 2023/2024. The geotechnical database was regenerated incorporating all the available geotechnical
data.
Figure 1. Historical Geotechnical Data (MEC 271100 CYM Geotechnical PFS – final V1.0)
Cyprium – Nifty Copper Operation | Page 5 of 15
Cyprium – Nifty Copper Operation
271019 – Pit Optimisation Update
Figure 2. Geotechnical drill hole Locations (2023 drilling) (MEC 271100 CYM Geotechnical PFS – final V1.0)
The study examined the overall rock mass analysis, bench scale rock mass stability and bench face angle stability,
inclusive of major structures. The resulting analysis generated overall slope, bench face angle and inter-ramp
angle recommendation for pit optimisation and design. These output parameters delivered a simplified
geotechnical zone plan, with improved overall slope angles in the majority of the modelled zones. Pit design
analysis of the Scoping study designs was also completed to test the failure modes and a confirmatory step, and
to inform the design process in the future study phases.
Cyprium – Nifty Copper Operation | Page 6 of 15
Cyprium – Nifty Copper Operation
271019 – Pit Optimisation Update
Figure 3. Summary overview of revised geotechnical zones and parameters.
3 OPTIMISATION
The pit optimisation was completed using Maptek Vulcan Pit optimiser, employing the Lerch Grossman
algorithm methodology like other optimisation software, e.g., Whittle.
All Vulcan Pit Optimisations were evaluated on a contained copper basis and calculated using block model
scripting and interface inputs in accordance with the assumptions noted in section 2.
3.1
Optimisation Results
3.1.1
Shell Generation
The pit optimisation was completed generating shells for a span of revenue factors from 0.6 to 1.2, the resulting
in pit shells allow for selection of final pit extents and phase groupings for analysis and then future design.
Cyprium – Nifty Copper Operation | Page 7 of 15
Cyprium – Nifty Copper Operation
271019 – Pit Optimisation Update
Figure 4. Initial Optimisation Overview
Figure 5. Optimisation pits long-section with Scoping study pit design.
Cyprium – Nifty Copper Operation | Page 8 of 15
Cyprium – Nifty Copper Operation
271019 – Pit Optimisation Update
Figure 6. Optimisation pits cross-section with Scoping study pit design.
Pits were then examined to determine the key phase groupings based on pit positions and physicals for practical
mining phase shapes, selection pits are shown in Table 2.
Table 2. Initial optimisation pit physicals.
it selected to guide stage design
it selected to guide nal pit design
Cyprium – Nifty Copper Operation | Page 9 of 15
Cyprium – Nifty Copper Operation
271019 – Pit Optimisation Update
3.1.2
Pit Phases
The initial optimisation pits were then grouped into suitable pit phases to enable minable phases to be
represented. A total of 7 pit phases were considered for this analysis, these phases are required to be further
rationalised and grouped in the future pit design works.
Figure 7. Pit phases overview
Figure 8. Pit extents with Resource category overlay.
Cyprium – Nifty Copper Operation | Page 10 of 15
Cyprium – Nifty Copper Operation
271019 – Pit Optimisation Update
Figure 9. Optimiser pit phases long-section and Scoping pit design.
Figure 10. Optimiser pit phases cross-section and Scoping pit design.
Cyprium – Nifty Copper Operation | Page 11 of 15
Cyprium – Nifty Copper Operation
271019 – Pit Optimisation Update
800Mt
Fresh
Transitional
Oxide
Waste
700Mt
Tonnage
600Mt
500Mt
400Mt
300Mt
200Mt
100Mt
0Mt
1
2
3
4
Pit
5
6
7
Figure 11. Pit phase physicals
3.2
High Level Schedule
Phased pits were analysed at production levels aligned to the Scoping study, modelling both the total mining
and concentrator feed. This analysis was generated to examine potential timing of surface infrastructure
interaction, and to inform potential changes in pit planning in study work. The output is not to be taken as
detailed scheduling and should not be utilised for forward looking economic examination.
Figure 12. High level physicals per year.
Cyprium – Nifty Copper Operation | Page 12 of 15
Cyprium – Nifty Copper Operation
271019 – Pit Optimisation Update
4
OUTCOMES & RECOMMENDATIONS
The resultant pit extents with the revised geotechnical parameters demonstrate significant reductions in the
overall pit size, delivering an improved stripping ratio from the Scoping study at 9.7:1 to approximately 7.3:1 on
a comparable basis, see Table 3 . This decrease in the pit extents delivers a material difference in the timing that
the mining activities will likely impact the existing Solvent Extraction and Electro Winning (SX-EW) facilities,
compared the initial Scoping study pits, see Figure 13.
Table 3. Optimisation phase physicals.
Figure 13. Pit phases versus Scoping pit with SXEW infrastructure.
Cyprium – Nifty Copper Operation | Page 13 of 15
Cyprium – Nifty Copper Operation
271019 – Pit Optimisation Update
The change in pit phase timing presents potential to maintain the SXEW plant for the first half of the mine life,
based on high level sequences. This is a material change as the Scoping study assumed that the Oxide ores within
the pit were to be treated as waste, with no maintainable processing facilities to enable metal recovery of this
material stream. Considering the potential Oxide ore processing stream, MEC modelled the Oxide ores that
existed in the waste profile for the Sulphide pit. This material has not been assessed for financial viability in this
optimisation study. The potential oxide tonnes and their timing have been calculated demonstrating the
majority of the resource classified tonnes are mined predominately in the first four years. Inclusion of the oxide
ore potential would further improve the project stripping ratio to 6.3:1 should the full oxide be economic.
4.1
Recommended Further Work
MEC recommend that a potential Oxide stream be explored in the next phase of studies, including detailed
economic analysis of the oxide processing stream with consideration of the oxide being stripped in the sulphide
pit sequence.
Cyprium – Nifty Copper Operation | Page 14 of 15
Cyprium – Nifty Copper Operation
271019 – Pit Optimisation Update
DOCUMENT CHANGE CONTROL
Description of
Version
1.
2.
3.
Author (s)
Changes/amendments
Christofer
Written
Edited
Rodrick Bonner
with
Cyprium
review
Cyprium
review
considered
Edited
Catania,
with
considered
Date
05/09/2024
Christofer Catania,
06/09/2024
Christofer Catania,
07/09/2024
4
Revised headers for release
Christofer Catania,
08/09/2024
5
Reviewed &Finalised
Christofer Catania,
11/09/2024
Status
Final
Version
5
Print Date
11/09/2024
Author(s)
Rodrick Bonner, Christofer Catania
Reviewed By
Christofer Catania
Pathname
CustData/271000_Cyprium/271019 Optimisation Update/Reports
File Name
MEC 271019 - Cyprium Metals - Optimisation V05_Final
Job No
271019
Distribution
Cyprium Metals
DOCUMENT REVIEW AND SIGN OFF
Version
Reviewer
Position
Signature
3.
Christofer
Principal Advisor/ CEO
Date
11/09/24
Catania
Cyprium – Nifty Copper Operation | Page 15 of 15