SEPTEMBER 2026 QUARTERLY ACTIVITIES REPORT
Cyprium Metals Limited (ASX: CYM / OTCQB: CYPMF) (Cyprium or the Company), a copper developer
focused on the phased restart of the Nifty Copper Complex in the Paterson region of Western Australia
(Nifty), is pleased to report its quarterly activities for the period ended 30 September 2026 (September
quarter).
HIGHLIGHTS
• Up to A$83 million1
debt and equity funding package to accelerate next phase of growth
(post quarter)
- A$21 million two tranche equity placement and A$5 million SPP
- Proposed US$40 million two tranche extension to existing senior secured facility
• Phase 1 Cathode Restart commissioning commenced
- Commissioning of ponds and heap leach pad infrastructure
- First leach, with heap leach operations now ramping towards commercial volumes
- Solvent Extraction (SX) plant module into commissioning
- Electrowinning (EW) area refurbished with installation of anodes at 80%
- Rectiformer and transformer installed and nearing energisation post quarter
- HV power connected from power plant to SXEW plant area
- Zero lost time injuries (LTIs) maintained from start of construction
• Direct injection leaching mine plan significantly de-risked
- Well designs and spacing confirmed
- Commercial flow rates on both high and low pressure injections
- Confirmation of leach chemistry during commissioning
• First copper cathode production expected in the coming weeks during wet commissioning
and ramp up
• Continued advancement of technical work to support near-term growth at Nifty through
expanding SXEW cathode production capacity and delivery of DFS on new open-pit mine that
recovers remaining oxides for cathode production and accesses the large sulphide Reserve
below
• Cyprium well-funded to advance all key workstreams: A$37.6M cash at quarter-end and up
to A$83 million funding package announced post quarter
1
Includes A$21 million of equity placement proceeds before costs, full utilisation of the proposed US$40 million extension to
existing senior secured debt facilities at AUD:USD 0.70, and full allotment of A$5 million SPP. Refer to important information
regarding forward-looking statements on page 16 of this release.
2
ASX: CYM |
Commenting on the September 2026 quarter, Cyprium Executive Chairman Matt Fifield, said:
“The critical workstreams completed and advanced during the September quarter have brought Nifty to the
threshold of copper cathode production. The dedication and expertise of our broader team and key
execution partners have been instrumental in progressing the final workstreams required to recommission
the SXEW plant. Importantly, this substantial progress has been achieved while maintaining an excellent
safety performance, with zero LTIs recorded during the quarter.
“On behalf of the Cyprium team, I look forward to providing further updates in the coming weeks as we
transition Nifty from a brownfields redevelopment project into Australia’s next great copper producer.”
FUNDING UPDATE - STAGED A$83 MILLION FUNDING PACKAGE
By separate release, Cyprium today announced a debt and equity funding package of up to A$83 million2
to
support delivery of open-pit DFS, expansion of SXEW plant capacity to above 20,000 tonnes Cu per annum,
and investment into early works and enabling infrastructure at Nifty Copper Complex.
The funding package comprises:
• A$21 million two tranche Placement supported by new and existing domestic and international
institutional shareholders. Placement offered at A$0.330 per share, a 9.6% discount to the last traded
price prior to the capital raise.
• A$5 million Share Purchase Plan (SPP), providing eligible existing shareholders the opportunity to
participate on the same terms as the Placement.
• US$40 million proposed extension to the existing senior secured debt facility (Tranche 1),
comprising:
- US$25 million Tranche 2 (A$36m).
- US$15 million Tranche 3 (A$21m).
The proposed US$40 million extension is subject to completion and signing of binding full form
documentation and other conditions, including completion of confirmatory lender due diligence.
Cyprium and its lender have entered a 30-business day exclusivity period to negotiate binding terms
and completion of lender confirmatory due diligence.
For further details on the funding package refer to Cyprium’s announcement “Up to A$83M funding to
Accelerate Next Stages of Growth” released to the ASX announcements platform on 30 October 2026.
3
ASX: CYM |
PHASE 1 COPPER CATHODE RESTART – OPERATIONS UPDATE
The following provides an update on the progress of the Phase 1 Cathode Restart over the September
quarter and up to the date of this announcement. Over this period, Cyprium focused on mechanical
completion, heap leach commissioning and operational readiness activities to position Nifty for the
completion of the Phase 1 Cathode Restart Project. Cyprium expects to achieve first copper cathode
production in the coming weeks during wet commissioning and ramp-up.
HEAP LEACH PADS AND LEACHING ACTIVITY
Heap commissioning activities commenced during the quarter, involving the introduction of acid solution
into the heaps for the first time in close to 20 years.
As previously reported, Cyprium is implementing direct injection leaching technology to the existing heaps
at Nifty following completion of a successful trial in August. 212 production and monitoring wells have been
established across the heap leach operational area. During the drill out of the wellfield, grade sampling
confirmed block model estimates within acceptable tolerances.2
The production area established by the installed well field accesses approximately 1.7 million tonnes of
material sufficient to support approximately six to eight months of leaching activity at projected recoveries.
As the operations deplete a production area, additional production blocks will be drilled, cased and
commissioned for direct injection.
Commissioning and ramp-up activities in the quarter have demonstrated the ability to achieve injection
volumes and flow rates in line with Company targets. Initial leach chemistry observations showed targeted
copper to acid ratios and rapid leaching kinetics.3
Drill out of production area Production areas drilled and cased
High pressure injection leaching Low pressure injection leaching
2
Cyprium’s current Mineral Resources estimates for the Nifty heaps as released to the ASX announcements platform on 19
August 2024 (release entitled: “Nifty Heap Leach Mineral Resource estimate”). Refer to important information regarding
Cyprium’s Mineral Resources estimates on page 16 of this release.
3
Refer to CYM announcement “Heap Leach Commissioning Update” released to the ASX announcements platform on 9
October 2026.
4
ASX: CYM |
PONDS AND SOLUTION INFRASTRUCTURE
Ponds and solution infrastructure required to support commencement of commercial production from the
existing heaps is now established and in commissioning. This infrastructure supports heap leach
operations by delivering solution volume targets capable of supporting commercial production.
During commissioning sulphuric acid has been added to the existing solution in the eastern ILS pond,
creating an acidified ILS that is then transported to the heaps. Regular deliveries to Nifty of sulphuric acid
to support heap leaching activities have commenced.
Solution off flow during heap operations Moving leaching solution
Collecting high grade solution High grade solution building in the ponds
Arial view of ponds and W-drains
5
ASX: CYM |
SOLVENT EXTRACTION PLANT
During the quarter, the SX plant mechanical refurbishment works were substantially completed and
commissioning activities (dry commissioning and commissioning with water) commenced. Post quarter
end, commissioning activities have continued, with electrical termination works finalised and bump testing
of motors and equipment completed upon reinstatement of LV power.
Mixer blade and rotor installed and bump tested Settler tank lids lifted into place
Pumps installed and commissioned Bump testing of motors
Progress highlights include:
• Completion of piping installation on all primary settling tanks (E1, E2, S1), crud and clay, and the
strong electrolyte, coalesced and loaded organic tank lines, and raffinate tanks
• Installation of pumps at loaded organic tank, loaded organic coalescer tank, strong electrolyte tank
and raffinate tank
• Completion of static hydrotesting of the coalescer and the loaded organic, EW and raffinate tanks
• Completion of diluent tanks and piping
• Completion of hazardous area (static electricity) audit
• Bump testing of motors and equipment ready for wet commissioning
6
ASX: CYM |
ELECTROWINNING PLANT
The EW plant was substantially mechanically completed during the quarter, with all major equipment
delivered and installed.
Post quarter, the team has worked to complete remaining scope, including installing cell top furniture,
completion of refurbishment of stripping machine and loading of anodes, as well as final completion of
electrical and instrumentation scope. Anodes have been loaded into the EW cells ready for wet
commissioning and ramp-up.
Installing anodes Cell top furniture and anodes installed
EW pipework installed Control room refurbished
Progress highlights include:
• Loading of anodes into EW cells (80% complete)
• Installation of cell top furniture
• Completion of refurbishment of the circulation tank, hydro test, and cell off-flow / on-flow headers
• Installation of reagent tanks and heat exchanger
• Refurbishment of stripping machine underway
• Completion of refurbishment of cathode scales, punch and strapper
• Completion of refurbishment of the control room.
7
ASX: CYM |
ELECTRICAL AND INSTRUMENTATION
Completion of physical installation and termination works of much of the electrical scope was completed
during the quarter.
As previously reported, delays to plant commissioning were encountered due to failure of existing high
voltage components during testing requiring procurement and expediting of replacement parts. The
Company has been able to partially recover schedule by progressing pre-commissioning activities
(bumping motors and pressurising pipes and valves) using auxiliary power.
Completion of the E&I scope is imminent, with the primary outstanding scopes being commissioning of the
rectiformer and energisation of the PLC. Following completion of these scopes, wet commissioning of the
plant can commence with the introduction of reagents and electrolyte.
Rectiformer installed Rectiformer busbar installed
Filling of rectifier cooling circuit with demineralised water MCC energised with LV power
Progress highlights include:
• Completion of construction of the rectiformer, including tie into the EW busbar
• Completion of HV cable runs connecting the rectiformer to power station
• Completion of the HV regulatory compliance process
• Completion of the MCC buckets
• Completion of all SX motors bump test on auxiliary power
• PLC/SCADA and instrumentation install progressing
8
ASX: CYM |
COMMISSIONING AND OPERATIONAL READINESS
Site activities across the period supported pre-commissioning and commissioning activities and
heightened operational readiness.
Pre-start meeting Firewater system installed
EW tank house flooring installed Scaffold removal
Progress highlights include:
• Completion of pipework and installation of fire water tanks
• Substantial completion of fire system and ring main
• Preparation of operations manual and procedures, along with development of training systems
• Completion of fit out of laboratories necessary to support production
• Acquisition of appropriate rescue, safety and hazmat equipment
• Initial deliveries of first fill material
• Establishment of warehouse stocktake and ERP protocol.
Shortly post quarter end, terms for the operation of the SXEW were finalised with PPM Global. PPM Global
is a specialist group with extensive experience operating SXEW plants, including personnel with direct
experience operating the Nifty SXEW prior to it being placed in care and maintenance in 2009. The PPM
Global team has also been involved in commissioning and acceptance activities as we look to complete
refurbishment activities and transition into operations.
9
ASX: CYM |
GROWTH ACTIVITIES
SXEW PLANT CAPACITY EXPANSION & SOURCES OF OXIDE FEED4
The expansion of cathode production capacity in the SX-EW plant is likely to be the next major growth step
beyond the current Phase 1 Cathode Restart project.
Cyprium is currently completing planning work and capital estimates to expand the refurbishment of the
SX-EW plant required to increase production capacity from the targeted ~6,000 tpa cathode production
capacity of the Phase 1 Cathode Restart project to ~20,000 tpa.
Nifty SXEW plant, process trains and shared components
The key enablers for plant expansion will be Cyprium’s ability to generate more copper in leach, either by
increasing mining rate of the existing heap leach pads and/or obtaining additional oxide material for
leaching operations from existing surface stockpiles and the open pit.
Near surface oxides and mineralised zones within waste dump5
4
Production cited is a reference to targeted production capacity of the SX-EW and not a production target. Refer to
important information regarding forward looking statements on page 16 of this release.
5
This figure shows preliminary drawings that are subject to change.
10
ASX: CYM |
Accelerated Leaching of Existing Heaps
The successful implementation of direct injection leaching and commissioning activities to-date have
demonstrated the potential to inject leaching solution at significantly higher volumes and rates than were
forecast for the traditional surface leach method, and with greater control over mine plan.6
The direct
injection method is expected to have the potential to produce PLS volumes in excess of the processing
rates of the refurbished B-Train of the SXEW plant (refurbishment scope under the current Phase 1
Cathode Production Restart project).
Open Pit Oxides
As outlined in the Nifty PFS7
, there is known shallow oxide material in the open pit at Nifty. For the
purposes of the Nifty PFS, this shallow oxide material was not included in the cathode operations on the
basis that further evaluation was required. As a result, the oxide material that was mined enroute to
reaching the sulphide ores was assumed to be stockpiled as waste, adding to cost but generating no
revenue, under the Nifty PFS.
Cyprium continues to advance its evaluation of the shallow oxide material, including undertaking additional
drilling and mine planning. Following completion of this work, Cyprium expects to report updated Mineral
Resources & Ore Reserves estimates for the Nifty Copper Complex during H1 CY2027.7
Oxide Resource location (oblique plan view)
Oxide Resource location (looking up and north)
6
Refer to important information regarding forward looking statements on page 16 of this release.
7
Refer to important information regarding the Nifty PFS on page 16 of this release.
11
ASX: CYM |
Nifty Waste Dump Mineralisation
As highlighted in Cyprium’s quarterly report for the June quarter, Cyprium reported the results of an RC drill
program to test an area of the Nifty waste dump hosting visible copper oxide mineralisation during the
September quarter.8
Oxide copper mineralisation within the waste dump presents a potential future low-cost source of feed to the
refurbished heap leach and SXEW. This material is located within 1.2km of the existing heap leach pads via
existing haul roads.
Primary mineralised zone within the Nifty waste dump with key intersections
8
Refer to CYM ASX announcement entitled “Drilling Identifies Extensive Copper Mineralisation Within Nifty Waste Dump”
released to the ASX announcements platform on 9 July 2026 for further information (including competent person’s
statement and JORC Code disclosures).
12
ASX: CYM |
DEFINITIVE FEASIBILITY STUDY
Cyprium has established a highly experienced in-house technical team to progress the Definitive Feasibility
Study (DFS) on the open pit activation and concentrator restart. The team is accelerating progress on the
DFS work scopes, with completion of the DFS targeted for H1 CY2027.
The DFS is planned to incorporate identifying opportunities for speed to revenue and increased capital
efficiency relative to the 2024 PFS outcomes.
A ~10,000m drilling program to support the DFS is well progressed, comprising resource infill, geotech and
metallurgical sampling drilling. Data from this work will contribute to update of the known oxide resource for
inclusion in the DFS mine plan and further definition of the oxide, transitional and sulphide layers to optimise
planning for processing routes and metallurgical recoveries.
Indicative DFS works scope timetable9
9
Refer to important information regarding forward-looking statements on page 16 of this release.
13
ASX: CYM |
EXPLORATION
In parallel to Phase 1 Cathode Restart and near-term growth project activities, exploration drilling and data
analysis continues.
NEAR NIFTY EXPLORATION
The first of six diamond holes targeting down plunge extensions to the Nifty deposit were drilled during the
quarter. Samples have been cut and submitted for assay, with results pending.
PATERSON
Towards the end of the quarter, site preparation commenced for an aircore drilling program aimed at testing
several areas within Cyprium’s Paterson tenement holding. Identified targets are located in the Broadhurst
Formation, which hosts the Nifty deposit, and in Lamil Group rocks, which host world-class copper-gold
deposits including Winu and Telfer.
RAINBOW
Final assay results from the Rainbow drilling program undertaken earlier in the year remain outstanding.
Initial assay results showed conflicting information during Cyprium’s strict QAQC processes and samples
have been sent to another lab for reprocessing.
Site preparation has commenced for a planned RC program at Rainbow and Rainbow South. The drill
program will test strike extensions to previously identified mineralisation and conceptual targets associated
with the basin-bounding Vines Fault.
MAROOCHYDORE
The Company continues to examine the potential for the Maroochydore Copper-Cobalt deposit to provide
additional ore feed to Nifty in a Paterson hub and spoke processing model.
CUE COPPER-GOLD
The Company continues to review its longer-term plans for the Cue Copper-Gold Project.
14
ASX: CYM |
CORPORATE
Annual Report and Corporate Governance Statement. On 30 September 2026, Cyprium released its
2026 Annual Report and Annual Corporate Governance Statement. As set out in the Annual Corporate
Governance Statement, Cyprium has adopted updated corporate governance policies and an updated
Board charter. Copies of the Company’s updated corporate governance documents are available via a
dedicated corporate governance page on the Company’s website and can be accessed here.
Annual General Meeting. Cyprium’s Annual General Meeting (AGM) will be held on 18 November 2026.
The Notice of Meeting, including details of the resolutions to be considered by shareholders, was released
on 19 October 2026.
FINANCE UPDATE
CASH FLOWS FROM OPERATING ACTIVITIES
Net cash used in operating activities during the September quarter was $7.7m. Expenditures related to
readying the site for copper cathode production operations, corporate support functions, interest payments
and progressing the Company’s growth-related initiatives.
Payment of $160,251 reported in item 6.1 of the attached Appendix 5B relates to Director remuneration and
superannuation (including the Executive Chairman).
CASH FLOWS FROM INVESTING ACTIVITIES
Net cash used in investing activities in the September quarter of $23.1m includes:
• $28.8m investment into property plant and equipment at the Nifty Copper Complex including heap leach
pads, ponds and solution infrastructure, acid storage facility, solvent extraction and electrowinning plant
and camp infrastructure;
• $1.4m net payments for exploration and evaluation; partially offset by
• $7.0m proceeds from sales of marketable securities.
CASH FLOWS FROM FINANCING ACTIVITIES
Net cash used in financing activities in the September quarter of $0.1m includes lease and other payments,
partially offset by proceeds from option conversions and the release of a bank guarantee.
CASH AND LIQUIDITY
The Company had A$37.6 million of cash on hand at 30 September 2026.
As noted above, post quarter end the Company announced an up to A$83 million funding package.
15
ASX: CYM |
This ASX announcement was authorised by the Cyprium Board.
For Enquiries:
Angus Miles | VP – Corporate Development and Investor Relations
+61 8 6374 1550
Chris Lim | External Media Relations Advisor
+61 493 392 001
communications@cypriummetals.com
Follow Cyprium Metals:
Subscribe to Email alerts https://cypriummetals.com/contact-us/subscribe-to-email-alerts/
LinkedIn https://www.linkedin.com/company/cyprium-metals/
X https://x.com/CypriumMetals
16
ASX: CYM |
IMPORTANT INFORMATION
FORWARD LOOKING STATEMENTS
This document contains statements and comments about future events, including in relation to Cyprium’s business, plans and
strategies, and expected events and trends in the industry in which Cyprium operates. Such statements and comments are
commonly referred to as forward-looking statements.
Forward-looking statements can generally be identified by the use of words such as “anticipate”, “believe”, “could”, “estimate”,
“expect”, “forecast”, “intend”, “likely”, “may”, “outlook”, “plan”, “predict”, “propose”, “should”, “target”, and “will”, and other similar
expressions. Indications of, and guidance and outlook commentary regarding, future earnings, financial performance and operating
performance are also forward-looking statements.
Readers are cautioned not to place undue reliance on forward-looking statements. Forward-looking statements involve inherent
risks, assumptions and uncertainties, both general and specific, and there is a risk that forward-looking statements will not be
achieved.
A number of important factors may result in Cyprium’s actual results and performance differing (including materially) from the plans,
objectives, estimates, targets and intentions expressed in forward-looking statements, and many of these factors are beyond the
control of Cyprium, its directors and management. Statements or assumptions in this document may prove to be incorrect, and
circumstances may change, and the contents of this document may become outdated as a result. This may include statements
about market and industry trends which are based on subjective interpretations of prevailing market conditions.
Unless otherwise stated, statements in this document regarding the Company’s plans reflect the Company’s plans at the time of
writing, which plans remain subject to one or more of changes as a result of ongoing technical work, regulatory approvals, securing
funding requirements and Board approval.
Forward-looking statements in this document are based on Cyprium’s good faith assumptions as to the financial, market, regulatory
and other relevant conditions that will exist and affect Cyprium’s business and operations in the future. Cyprium does not give any
assurance that these assumptions will prove to be correct. There could be other factors that may cause actual results, conditions or
events not to be as anticipated, many of which are beyond Cyprium’s reasonable control.
Forward-looking statements in this document speak only as at the date of this document and, expect where required by applicable
law, Cyprium does not intend to update or revise any forward-looking statements, nor to publish forward-looking statements in the
future, regardless of whether new information, future events or other factors affect the information contained in this document.
Nothing in this document is, or is intended to be, a promise or representation as to the future, and past performance is not a
guarantee of future performance. None of Cyprium, its directors or management make any representation or warranty as to the
accuracy of any forward-looking statements in this document.
NIFTY PFS
Cyprium published a pre-feasibility study for the Nifty Copper Complex (the Nifty PFS) on 27 November 2024 (announcement
entitled “Nifty PFS Confirms $1.129m Pre-Tax NPV and 797kt Ore Reserve” released to the ASX announcements platform on 27
November 2024).
Readers should refer to the Nifty PFS for detailed information regarding the study and study outcomes, including:
▪ Cautionary statements;
▪ Mineral Resources and Ore Reserves estimates, including competent person statements and JORC Code disclosures; and
▪ technical and financial assumptions underpinning the economic evaluation in the Nifty PFS.
MINERAL RESOURCES ESTIMATES
Cyprium prepares and reports its Mineral Resources estimates in accordance with the Australasian Code for Reporting Exploration
Results, Mineral Resources and Ore Reserves (2012) (the JORC Code). A reference in this release to Cyprium’s Mineral Resources
and Ore Reserves estimates for the Nifty Heap Leach is a reference to estimates reported in the following releases to the ASX
announcements platform:
▪ Mineral Resources estimates: 19 August 2024 (release entitled: “Nifty Heap Leach Mineral Resource Estimate”); and
▪ Ore Reserves estimate: 27 November 2024 (release entitled: “Nifty PFS confirms $1.129m Pre-Tax NPV and 797kt Ore
Reserve”).
Refer to these above releases for further information, including competent person’s statements and JORC Code disclosures.
17
ASX: CYM |
APPENDIX A
ANNOUNCEMENTS IN THE SEPTEMBER QUARTER 2026
Shareholders are encouraged to visit cypriummetals.com/investor-centre for comprehensive information
on announcements made during the September quarter 2026. This Quarterly Activities Report summarises
key updates extracted from ASX market announcements, which have been prepared in accordance with
the 2012 edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources, and Ore
Reserves (JORC Code, 2012). For additional details, including JORC Code reporting tables where relevant,
please refer to the ASX announcements listed within this report.
Date Announcement
25/06/2026 Operations Update – Nifty Copper Complex
26/06/2026 Executive Appointment
09/07/2026 Extensive Copper Mineralisation Within Nifty Waste Dump
17/07/2026 Quarterly Activities/Appendix 5B Report – June 2026 Quarter
21/07/2026 Change in substantial holding
24/07/2026 Noosa Mining Conference Presentation
24/07/2026 Noosa Mining Conference Presentation (Updated)
04/08/2026 Diggers & Dealers Presentation
21/08/2026 Response to ASX Price Query
25/08/2026 Becoming a substantial holder
14/09/2026 Operations Update – Phase 1 Cathode Restart Project
24/09/2026 Notification regarding cessation of securities – CYM
24/09/2026 Change of Director’s Interest Notice
30/09/2026 2026 Annual Report to Shareholders
30/09/2026 Corporate Governance Statement and Appendix 4G
18
ASX: CYM |
APPENDIX B
TENEMENT INFORMATION
Tenement Location Interest
Cyprium has a 100% interest in the Nifty Copper Complex, WA,
which comprises the following tenements:
M271SA, L45/74, L45/91, L45/102, L45/128, L45/143, L45/148,
E45/6263, M45/752, M45/753, M45/754 and P45/3177.
Paterson Province,
WA
100%
Cyprium has a 100% interest in the Maroochydore Copper Project,
WA, which comprises the following tenements:
E45/1840, E45/1841, E45/3011, E45/4318, E45/4319, M45/314,
M45/315, M45/317, M45/318, M45/492, M45/711, M45/712,
M45/713, M45/745, M45/746 and P45/3055.
Paterson Province,
WA
100%
Cyprium has a 100% interest in the Paterson Exploration Project,
WA, which comprises the following tenements:
E45/1839, E45/2280, E45/2415, E45/2771, E45/2772, E45/2773,
P45/2792, P45/2793, P45/2794, P45/2801, P45/2802, P45/2803,
P45/2804, P45/2805, P45/2806, P45/2807, P45/2808, E45/3573,
E45/3574, E45/3575, E45/3577, E45/4151, E45/4205, E45/4234,
E45/4862, E45/5199, E45/5300, M45/1109, M45/1110, M45/1111,
M45/1112, M45/1113, M45/1114, E45/7194, E45/7195, E45/7197,
ELA45/7196, ELA45/7293, ELA45/7300 and ELA45/7309.
Paterson Province,
WA
100%
Cyprium has an 80% joint venture interest in the Cue Copper-Gold
Project’s copper, gold and silver mineralisation; Ramelius Resources
Limited (ASX Code: RMS) has a 100% interest in primary gold
deposits not associated with copper-gold mineralisation, for the
following tenements in WA:
L20/90, M20/225, M20/245, M20/277, M20/526, E20/606, E20/616,
E20/630 and E20/659
Murchison
Province, WA
80%
Changes to Tenement Holdings in the Quarter
• Paterson exploration licence applications ELA45/7293, ELA45/7300 and ELA45/7309 filed
19
ASX: CYM |
ABOUT US
Cyprium Metals Limited (ASX: CYM / OTCQB: CYPMF) is an ASX-listed Australian copper company. Its flagship
property is the Nifty Copper Complex in Western Australia, which previously produced significant copper from
both oxide and sulphide resources. Cyprium is focused on redeveloping Nifty, which has the advantage of
significant invested capital, data from a long operating history, large-scale resources, current operational
approvals, and recent investment in the property.
The Company’s other assets include significant copper-focused properties in the Paterson and Murchison
Provinces, including multiple defined resources.
For more information, visit: www.cypriummetals.com
Near-term Producer Fast-track restart with low capex and near-term cash
flow from heap leach reprocessing
Advantage Tier-one copper assets in Western Australia with existing
infrastructure and permits in place
Exploration Highly prospective copper targets at Paterson and Cue
support long-term growth pipeline