Quarterly Activities/Appendix 5B Cash Flow Report
Released
Released
Announcement PDF
ASX Announcement
ASX: CYM | 17 JULY 2026
T +61 8 6374 1550
E communications@cypriummetals.com
W cypriummetals.com
Level1, 437 Roberts Road
Subiaco WA 6008
AUSTRALIA
Cyprium Metals Limited
ABN: 48 002 678 640
ASX: CYM
JUNE 2026 QUARTERLY ACTIVITIES REPORT
HIGHLIGHTS
• Phase 1 Cathode Restart advancing rapidly towards practical completion
- Site infrastructure work packages nearing completion
- New acid terminal commissioned; sulphuric acid deliveries to Nifty have recommenced
- Leach solution recovery and handling circuits advancing toward commissioning
- Commenced hydro-testing surface leach and injection leach programs on heap leach
- All significant capital items and first fills either delivered or dispatched to site
- Continued progress around regulatory sign-off on acid handling areas
• Targeting commencement of copper cathode production in the September Quarter 2026
• Continued advancement of technical work supporting near-term growth at Nifty Copper
Complex through a new open-pit mine that recovers remaining oxides for cathode production
and accesses the large sulphide Reserve below
• Extensive copper mineralisation identified within Nifty waste dump, including:
- 9m @ 1.00% Cu from 0m, incl. 4m @ 1.83% Cu from 2m in 26NFLG050
- 7m @ 1.11% Cu from 0m, incl. 3m @ 1.55% Cu from 2m in 26NFLG060
- 9m @ 0.80% Cu from 0m, incl. 2m @ 1.56% Cu from 5m in 26NFLG021
- 7m @ 0.90% Cu from 0m, incl. 3m @ 1.50% Cu from 1m in 26NFLG026
- 8m @ 0.86% Cu from 0m, incl. 5m @ 1.16% Cu from 0m in 26NFLG055
• Further targeted recruitment to support Cyprium’s production and growth strategy
- Richard Holmes as Chief Development Officer
- Christofer Catania as Chief Technology Officer
• Cyprium well-funded to advance all key workstreams: A$68.5M cash at quarter-end
Cyprium Metals Limited (ASX: CYM / OTCQB: CYPMF) (Cyprium or the Company), a copper developer
focused on the phased restart of the Nifty Copper Complex in the Paterson region of Western Australia
(Nifty), is pleased to report its quarterly activities for the period ended 30 June 2026 (June quarter).
Commenting on the June 2026 quarter, Cyprium Executive Chairman Matt Fifield, said:
“We have delivered significant progress on dual fronts over the June quarter. The Phase 1 Cathode Restart
at Nifty has advanced significantly with key works materially advancing. We are nearing a pivotal inflection
from construction and installation to delivery of the SXEW plant. Our team is proud of the progress made to
date and we remain on track for first cathode production this quarter.
2
ASX: CYM |
PHASE 1 COPPER CATHODE RESTART PROJECT
During the June quarter, Cyprium materially advanced the Phase 1 Copper Cathode Restart. As work
packages start to conclude, the Company’s focus is shifting from construction and refurbishment activities
to practical completion, commissioning and operational readiness.
A summary of the Phase 1 Cathode Restart activities is provided below. For a detailed update, please see
recent company announcement Operations Update: Nifty Copper Complex dated 25 June 2026.
Ponds and solution infrastructure
• Acid storage and
distribution terminal
Completed construction and
commissioning of the new acid storage
and distribution terminal
Following regulatory sign-off, sulphuric
acid deliveries recommenced in late-
May – the first acid on site since the
plant was placed in care and
maintenance in 2009
Acid terminal receiving first acid delivery
Off-flow piping discharging copper rich solution
• Ponds relining works Ponds relining works nearing
completion
• Installation of leach
solution transport
infrastructure
Materially progressed, including
reinstallation of solution pipes across
the system and installation of new
pumps, cable trays and control circuits
• Stormwater
management
Stormwater discharge system
adequacy confirmed
Heap leach pads and leaching activity
• Heap turnover and
dripper line installation
Continued physical turnover of heaps
and installed dripper lines
Testing direct injection leach system with water
• Testing of heap solution
systems
Testing and pressurisation of solution
systems
• Direct injection leaching
trial
Commenced trial of direct injection
leaching. Trial is testing the potential to
increase volume of material under
leach by applying solution via vertical
injection. Initial indications from the
trial program have been promising,
with the wellfield flushed with water
3
ASX: CYM |
SXEW Plant Refurbishment
• Refurbishment of Train B
of the existing SXEW
plant
Works undertaken in the quarter
included:
• Concrete repairs and acid proof
coating works nearing completion
• Reinstatement of pipework
throughout the system
• Installation of new pumps and
motors throughout the system
• EW cell insets delivered to site,
installation progressing
• EW busbar upgrade and
reinstallation completed
• Rectiformer and transformer
delivered to site
• Rectiformer pad installation
underway
• Overhead crane installed and
commissioned
• Stripping machine cleaned,
inspected and components
replaced
• Anodes delivered to site
All significant outstanding capital items
are either delivered or dispatched for
delivery to site
Acid proofing at mixer settlers complete
Installing fiberglass inserts for EW cells
Motor Control Centre cabling
• Controls and
instrumentation for the
entire SXEW plant
E&I works were a sustained focus over
the quarter. The integrated team is
progressing a large program of cable
removal, installation, testing and
termination across the motor control
centre and corresponding field areas
Commissioning and operational readiness
• Operating procedures
and training
Operational readiness momentum
maintained over the quarter
Development of operating systems and
processes continued to progress and
is on track to support heap leach and
plant commissioning and operations
Upgraded training systems, warehouse
stock management systems and ERP
protocols
Fitout of laboratories necessary to
support production
Acquisition of appropriate safety and
hazmat equipment to support
emergency response function
Site activity coordination meeting
• First fills Initial deliveries of reagent first fills
received to site
4
ASX: CYM |
Images, videos and interviews with respect to the Phase 1 Copper Cathode Restart project delivery activities
are available to view on the Company’s website.
SULPHURIC ACID SUPPLY
Since June, sulphuric acid prices across key seaborne markets have stabilised at elevated prices. Cyprium
continues to monitor the sulphuric acid market closely and key suppliers continue to confirm that the physical
availability of sulphuric acid to Nifty does not present a material risk to the Company’s current business plan
or future growth ambitions.
PROJECT OUTLOOK1
Cyprium is entering the final phase of delivering the Phase 1 Copper Cathode Restart project. In the
September quarter, execution focus shifts to heap leach commissioning, completion of construction and
refurbishment work packages, plant practical completion and commissioning, and first copper cathode
production.
GROWTH ACTIVITIES1
During the June quarter, Cyprium materially advanced technical and commercial work to mature and refine
the Company’s growth plan. A summary of progress is set out below.
Cyprium expects to provide further updates during the September quarter.
SXEW PLANT CAPACITY EXPANSION & OPEN PIT OXIDES
Cyprium materially progressed key workstreams associated with potential expansion of SXEW cathode
production capacity during the quarter, including:
• capital and operating cost estimates for extending refurbishment of the SXEW plant to A Train,
construction of a new pad 7, and mining the shallow in-pit oxide ore;
• ongoing evaluation of oxide material in pit and additional mineralised zones within the Nifty waste dump
to improve geological confidence; and
• mine planning work to accelerate potential to access in-pit oxide ores.
SXEW Plant Expansion
In parallel to the current Phase 1 Copper Cathode Restart project, Cyprium is advancing its evaluation of
opportunities to expand cathode production from the targeted ~6,000 tpa cathode production capacity
(Phase 1 Restart), to an expanded ~20,000 tpa2
cathode production capacity. An expansion of the SXEW
production capacity would seek to further leverage infrastructure that is being refurbished in Stage 1 to
rapidly increase cathode production capacity.3
The existing Nifty SXEW plant comprises two independent process trains and additional shared components
servicing both process trains – “A Train” and “B Train” – and shared control systems (see Figure 1).
1
Refer to important information on page 11 of this announcement regarding forward looking statements.
2
Production cited is a reference to targeted production capacity of the SXEW and not a production target. Refer to important information
regarding forward looking statements on page 11 of this release.
3
The existing SXEW plant at Nifty historically produced at a peak annual production rate of 25,000 tpa.
5
ASX: CYM |
• The Nifty SXEW Plant was built over time in a series of expansions until it reached its maximum
productive capacity of 25,000 tonnes
• The “B Train”, which Cyprium is currently bringing online, involves the newest areas of the plant,
including three mixer settlers, 42 EW cells, and many of the core components and instrumentation
required to run the entire plant
• Given Cyprium’s investment to re-establish the core components, expansion of productive capacity
would mainly entail refurbishment of additional cells and mixer settlers in the older and larger “A
Train”
Figure 1: Nifty SXEW plant, process trains and shared components4
As a part of the larger site-wide growth strategy, Cyprium is evaluating the potential for additional oxide ore
sources, including: (1) the shallow oxide material in the open pit identified in the Nifty Copper Complex PFS
(Nifty PFS); (2) mineralised zones within the waste dump identified at site; (3) as well as the potential to
recover copper from the existing pads at a higher rate (see Figure 2). Additional ore sources and/or an
increase in the rate of recovery from the existing pads would require an expanded capacity in the Nifty
SXEW, and newly mined oxide ore would likely require the construction of a new pad 7 for leaching
operations.5
4
Statements regarding productive capacity are an estimate of the potential to produce at an annualised volume and not a production target.
Refer to important information on page 11 of this release regarding forward looking statements.
5
Refer to important information regarding the Nifty PFS on page 11 of this release.
6
ASX: CYM |
Figure 2: Near surface oxides and mineralised zones within the waste
dump have potential to support additional cathode production capacity6
Open Pit Oxides
As outlined in the Nifty PFS7
, there is known shallow oxide material in the open pit at Nifty. For the purposes
of the Nifty PFS, this shallow oxide material was not included in the cathode operations on the basis that
further evaluation was required. As a result, the oxide material that was mined enroute to reaching the
sulphide ores was assumed to be stockpiled as waste.
Cyprium has advanced its evaluation of the shallow oxide material, including undertaking additional drilling
and mine planning. Following completion of this work, Cyprium expects to report updated Mineral Resources
& Ore Reserves estimates for the Nifty Copper Complex during the second half CY2026.
OPEN PIT SULPHIDES AND CONCENTRATOR
Cyprium continues to refine the Company’s plans regarding open pit mining and the refurbishment of the
existing Nifty concentrator, including expected capital costs, mine engineering and scheduling and operating
costs.
6
This figure shows preliminary drawings that are subject to change. Statements regarding productive capacity are an estimate of the
potential to produce at an annualised volume and not a production target. Refer to important information on page 11 of this release
regarding forward looking statements.
7
Refer to important information regarding the Nifty PFS on page 11 of this release.
7
ASX: CYM |
EXPLORATION
Cyprium’s exploration team has materially progressed exploration plans during the quarter and are awaiting
results from earlier drill programs. The Company plans to provide a separate update on exploration plans
during the September quarter.
NIFTY WASTE DUMP MINERALISATION
Post quarter-end, Cyprium announced the results of a recently completed RC drill program to test an area
of the Nifty waste dump hosting visible copper oxide mineralisation.8
Oxide copper mineralisation within the waste dump presents a potential future low-cost source of feed to the
refurbished heap leach and SXEW. This material is located within 1.2km of the existing heap leach pads via
existing haul roads.
The drill program was concentrated in an area of approximately 750m long and 250m in width (see Figure 3
and 4), with drill holes completed on a 40m x 40m grid with the central area infilled to 20m x 20m. A total of
133 holes were drilled for 2,697m, intersecting extensive copper oxide mineralisation throughout.
Significant drilling intercepts include:
• 9m @ 1.00% Cu from 0m, incl. 4m @ 1.83% Cu from 2m in 26NFLG050
• 7m @ 1.11% Cu from 0m, incl. 3m @ 1.55% Cu from 2m in 26NFLG060
• 9m @ 0.80% Cu from 0m, incl. 2m @ 1.56% Cu from 5m in 26NFLG021
• 7m @ 0.90% Cu from 0m, incl. 3m @ 1.50% Cu from 1m in 26NFLG026
• 8m @ 0.86% Cu from 0m, incl. 5m @ 1.16% Cu from 0m in 26NFLG055
• 15m @ 0.45% Cu from 2m, incl. 3m @ 1.58% Cu from 2m in 26NFLG002
• 13m @ 0.45% Cu from 6m, incl. 2m @ 2.03% Cu from 17m in 26NFLG009
• 6m @ 0.94% Cu from 0m, incl. 4m @ 1.15% Cu from 1m in 26NFLG097
• 6m @ 0.90% Cu from 0m, incl. 3m @ 1.12% Cu from 2m in 26NFLG095
• 24m @ 0.43% Cu from 0m, incl. 3m @ 1.35% Cu from 1m in 26NFLG094
In addition to the central waste dump drilling, 38 scout holes spaced at ~100m intervals along easily
accessible haul roads, were completed for 797m (see Figure 2). Several holes returned encouraging
mineralisation requiring follow up drilling, results include:
• 3m @ 0.88% Cu from 18m, incl. 1m @ 1.36% Cu from 18m in 26NFLG069
• 1m @ 1.33% Cu from 0m in 26NFLG118
• 6m @ 0.38% Cu from 0m, incl. 1m @ 1.21% Cu from 2m in 26NFLG035
• 6m @ 0.53% Cu from 10m, incl. 1m @ 1.89% Cu from 11m in 26NFLG143.
Refer to Cyprium’s 9 July 2026 release for full details of the drilling results, including competent person’s
statement and JORC Code disclosures.
8
Refer to CYM ASX announcement “Drilling Identifies Extensive Copper Mineralisation Within Nifty Waste Dump” dated 9 July 2026.
8
ASX: CYM |
Figure 3: Nifty waste dump drilling locations and scout holes
Figure 4: Primary mineralised zone within the Nifty waste dump with key intersections
NEAR NIFTY EXPLORATION
During the quarter, Cyprium progressed planning of a diamond drilling program targeting down plunge
extensions to the Nifty deposit. The proposed program will infill and extend through gaps in drill coverage to
test approximately 800m down plunge from the currently defined Nifty Resource. It is anticipated that, if
successful, drilling may support an extension of the current Resource.
9
ASX: CYM |
PATERSON
During the quarter, Cyprium progressed planning of a regional exploration program targeting mineralisation
in the Broadhurst Formation, which hosts the Nifty deposit, and in Lamil Group rocks, which host world-class
copper-gold deposits including Winu and Telfer.
Airborne EM data acquired in historic surveys over Cyprium’s Paterson Exploration Project has been
evaluated and anomalies identified. Heritage clearances were undertaken on high priority targets to facilitate
planned drill programs.
RAINBOW
As previously reported, a drilling program comprising eight diamond holes for 1,169 metres was completed
at the Rainbow Prospect during the March quarter. Drilling tested the WMC +100ppm Cu lag anomaly over
a strike length of 1.2 kilometres in an area where historic holes returned significant Cu-Ag intercepts.9
See
Figure 7 for Cyprium drill hole locations.
Final assays and evaluation for the March quarter drilling is ongoing. The Company expects to update the
market on the results and follow up exploration plans later this month.
Figure 5: Rainbow drillhole locations
MAROOCHYDORE
The Company continues to examine the potential for the Maroochydore Copper-Cobalt deposit to provide
additional ore feed to Nifty in a Paterson hub and spoke processing model.
CUE COPPER-GOLD
The Company continues to review its longer-term plans for the Cue Copper-Gold Project.
9
Refer to CYM ASX announcement “Significant Opportunities Identified Across the Paterson Exploration Project” dated 20 January 2026.
10
ASX: CYM |
CORPORATE
RECENT APPOINTMENTS
Cyprium strengthened its internal capabilities with targeted appointments during the quarter to support
execution of the Company’s strategy. Key appointments during the quarter included:
• Richard Holmes – Chief Development Officer; and
• Chris Catania – Chief Technical Officer.
FINANCE UPDATE
CASH FLOWS FROM OPERATING ACTIVITIES
Net cash used in operating activities during the June quarter was $5.0m. Expenditures related to readying
the site for copper cathode production operations, corporate support functions and progressing the
Company’s growth-related initiatives.
Payment of $181,084 reported in item 6.1 of the attached Appendix 5B relates to Director remuneration and
superannuation (including the Executive Chairman).
CASH FLOWS FROM INVESTING ACTIVITIES
Net cash used in investing activities in the June quarter of $22.7m includes:
• $20.6m investment into property plant and equipment at the Nifty Copper Complex including heap leach
pads, ponds and solution infrastructure, acid storage facility, solvent extraction and electrowinning plant
and camp infrastructure; and
• $2.1m net payments for exploration and evaluation.
CASH FLOWS FROM FINANCING ACTIVITIES
Net cash used in financing activities in the June quarter of $0.2m includes lease and other payments, partially
offset by proceeds from the release of a bank guarantee.
CASH AND LIQUIDITY
The Company had A$68.5 million of cash on hand at 30 June 2026.
The company holds 3,000,000 shares in Solstice Minerals Limited valued at $7.1m as at 30 June 2026.
This ASX announcement was authorised by the Cyprium Board.
11
ASX: CYM |
For Enquiries:
Angus Miles | VP – Corporate Development and Investor Relations
+61 8 6374 1550
Chris Lim | External Media Relations Advisor
+61 493 392 001
communications@cypriummetals.com
Follow Cyprium Metals:
Subscribe to Email alerts https://cypriummetals.com/contact-us/subscribe-to-email-alerts/
LinkedIn https://www.linkedin.com/company/cyprium-metals/
X https://x.com/CypriumMetals
IMPORTANT INFORMATION
FORWARD LOOKING STATEMENTS
This document contains statements and comments about future events, including in relation to Cyprium’s business, plans and strategies, and expected
events and trends in the industry in which Cyprium operates. Such statements and comments are commonly referred to as forward-looking statements.
Forward-looking statements can generally be identified by the use of words such as “anticipate”, “believe”, “could”, “estimate”, “expect”, “forecast”,
“intend”, “likely”, “may”, “outlook”, “plan”, “predict”, “propose”, “should”, “target”, and “will”, and other similar expressions. Indications of, and
guidance and outlook commentary regarding, future earnings, financial performance and operating performance are also forward-looking statements.
Readers are cautioned not to place undue reliance on forward-looking statements. Forward-looking statements involve inherent risks, assumptions and
uncertainties, both general and specific, and there is a risk that forward-looking statements will not be achieved.
A number of important factors may result in Cyprium’s actual results and performance differing (including materially) from the plans, objectives,
estimates, targets and intentions expressed in forward-looking statements, and many of these factors are beyond the control of Cyprium, its directors
and management. Statements or assumptions in this document may prove to be incorrect, and circumstances may change, and the contents of this
document may become outdated as a result. This may include statements about market and industry trends which are based on subjective
interpretations of prevailing market conditions.
Unless otherwise stated, statements in this document regarding the Company’s plans reflect the Company’s plans at the time of writing, which plans
remain subject to one or more of changes as a result of ongoing technical work, regulatory approvals, securing funding requirements and Board
approval.
Forward-looking statements in this document are based on Cyprium’s good faith assumptions as to the financial, market, regulatory and other relevant
conditions that will exist and affect Cyprium’s business and operations in the future. Cyprium does not give any assurance that these assumptions will
prove to be correct. There could be other factors that may cause actual results, conditions or events not to be as anticipated, many of which are beyond
Cyprium’s reasonable control.
Forward-looking statements in this document speak only as at the date of this document and, expect where required by applicable law, Cyprium does
not intend to update or revise any forward-looking statements, nor to publish forward-looking statements in the future, regardless of whether new
information, future events or other factors affect the information contained in this document.
Nothing in this document is, or is intended to be, a promise or representation as to the future, and past performance is not a guarantee of future
performance. None of Cyprium, its directors or management make any representation or warranty as to the accuracy of any forward-looking statements
in this document.
Nifty PFS
Cyprium published a pre-feasibility study for the Nifty Copper Complex (the Nifty PFS) on 27 November 2024 (announcement entitled “Nifty PFS
Confirms $1.129m Pre-Tax NPV and 797kt Ore Reserve” released to the ASX announcements platform on 27 November 2024).
Readers should refer to the Nifty PFS for detailed information regarding the study and study outcomes, including:
▪ Cautionary statements;
▪ Mineral Resources and Ore Reserves estimates, including competent person statements and JORC Code disclosures; and
▪ technical and financial assumptions underpinning the economic evaluation in the Nifty PFS.
12
ASX: CYM |
APPENDIX A
ANNOUNCEMENTS IN THE JUNE QUARTER 2026
Shareholders are encouraged to visit cypriummetals.com/investor-centre for comprehensive information
on announcements made during the June quarter 2026. This Quarterly Activities Report summarises key
updates extracted from ASX market announcements, which have been prepared in accordance with the
2012 edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources, and Ore
Reserves (JORC Code, 2012). For additional details, including JORC Code reporting tables where relevant,
please refer to the ASX announcements listed within this report.
Date Announcement
23/04/2026 Change in substantial holding
30/04/2026 Executive Appointment
30/04/2026 Quarterly Activities/Appendix 5B Report – March 2026 Quarter
01/05/2026 Notification regarding unquoted securities – CYM
01/05/2026 Change of Director's Interest Notice
01/05/2026 Change of Director's Interest Notice
01/05/2026 Change of Director's Interest Notice
01/05/2026 Change of Director's Interest Notice
06/05/2026 RIU Resources Round-Up Presentation
19/05/2026 Change in substantial holding
25/06/2026 Operations Update – Nifty Copper Complex
26/06/2026 Executive Appointment
13
ASX: CYM |
APPENDIX B
TENEMENT INFORMATION
Tenement Location Interest
Cyprium has a 100% interest in the Nifty Copper Complex, WA,
which comprises the following tenements:
M271SA, L45/74, L45/91, L45/102, L45/128, L45/143, L45/148,
E45/6263, M45/752, M45/753, M45/754 and P45/3177.
Paterson Province,
WA
100%
Cyprium has a 100% interest in the Maroochydore Copper Project,
WA, which comprises the following tenements:
E45/1840, E45/1841, E45/3011, E45/4318, E45/4319, M45/314,
M45/315, M45/317, M45/318, M45/492, M45/711, M45/712,
M45/713, M45/745, M45/746 and P45/3055.
Paterson Province,
WA
100%
Cyprium has a 100% interest in the Paterson Exploration Project,
WA, which comprises the following tenements:
E45/1839, E45/2280, E45/2415, E45/2771, E45/2772, E45/2773,
P45/2792, P45/2793, P45/2794, P45/2801, P45/2802, P45/2803,
P45/2804, P45/2805, P45/2806, P45/2807, P45/2808, E45/3573,
E45/3574, E45/3575, E45/3577, E45/4151, E45/4205, E45/4234,
E45/4862, E45/5199, E45/5300, M45/1109, M45/1110, M45/1111,
M45/1112, M45/1113, M45/1114, E45/7194, E45/7195, E45/7197,
ELA45/7196, ELA45/7293, ELA45/7300 and ELA45/7309.
Paterson Province,
WA
100%
Cyprium has an 80% joint venture interest in the Cue Copper-Gold
Project’s copper, gold and silver mineralisation; Ramelius Resources
Limited (ASX Code: RMS) has a 100% interest in primary gold
deposits not associated with copper-gold mineralisation, for the
following tenements in WA:
L20/90, M20/225, M20/245, M20/277, M20/526, E20/606, E20/616,
E20/630 and E20/659
Murchison
Province, WA
80%
Changes to Tenement Holdings in the Quarter
• Paterson exploration licence applications ELA45/7293, ELA45/7300 and ELA45/7309 filed
14
ASX: CYM |
ABOUT US
Cyprium Metals Limited (ASX: CYM / OTCQB: CYPMF) is an ASX-listed Australian copper company. Its flagship
property is the Nifty Copper Complex in Western Australia, which previously produced significant copper from
both oxide and sulphide resources. Cyprium is focused on redeveloping Nifty, which has the advantage of
significant invested capital, data from a long operating history, large-scale resources, current operational
approvals, and recent investment in the property.
The Company’s other assets include significant copper-focused properties in the Paterson and Murchison
Provinces, including multiple defined resources.
For more information, visit: www.cypriummetals.com
Near-term Producer Fast-track restart with low capex and near-term cash
flow from heap leach reprocessing
Advantage Tier-one copper assets in Western Australia with existing
infrastructure and permits in place
Exploration Highly prospective copper targets at Paterson and Cue
support long-term growth pipeline
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 1
Appendix 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
CYPRIUM METALS LIMITED
ABN Quarter ended (“current quarter”)
48 002 678 640 30 June 2026
Consolidated statement of cash flows
Current quarter Year to date
$A’000 $A’000
1 Cash flows from operating activities
1.1 Receipts from customers - -
1.2 Payments for - -
(a) exploration & evaluation - -
(b) development (3,642) (14,151)
(c) production - -
(d) staff costs (1,190) (4,236)
(e) administration and corporate costs (1,630) (5,970)
1.3 Dividends received (see note 3) - -
1.4 Interest received 1,382 2,445
1.5 Interest and other costs of finance paid (1,145) (7,105)
1.6 Income taxes paid - -
1.7 Government grants and tax incentives - -
1.8 Other (provide details if material) 1,196 4,301
1.9 Net cash from / (used in) operating activities (5,029) (24,716)
2 Cash flows from investing activities
2.1 Payments to acquire or for:
(a) entities - -
(b) tenements - -
(c) property, plant and equipment (20,617) (33,357)
(d) exploration & evaluation (2,101) (6,032)
(e) investments - -
(f) other non-current assets - -
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 2
Consolidated statement of cash flows
Current Year to date
$A’000 $A’000
2.2 Proceeds from the disposal of: -
(a) entities - -
(b) tenements - -
(c) property, plant and equipment 3 5,320
(d) investments - -
(e) other non-current assets - 98
2.3 Cash flows from loans to other entities - -
2.4 Dividends received (see note 3) - -
2.5 Other (provide details if material) - -
2.6 Net cash from / (used in) investing activities (22,715) (33,971)
3 Cash flows from financing activities
3.1
Proceeds from issues of equity securities
(excluding convertible debt securities)
- 123,519
3.2 Proceeds from issue of convertible debt securities - -
3.3 Proceeds from exercise of options - -
3.4
Transaction costs related to issues of equity
securities or convertible debt securities
(75) (6,549)
3.5 Proceeds from borrowings - 41,852
3.6 Repayment of borrowings (191) (42,406)
3.7 Transaction costs related to loans and borrowings (2,134)
3.8 Dividends paid - -
3.9 Other 83 83
3.1 Net cash from / (used in) financing activities (183) 114,365
4
Net increase / (decrease) in cash and cash
equivalents for the period
(27,927) 55,678
4.1 Cash and cash equivalents at beginning of period 96,481 13,658
4.2
Net cash from / (used in) operating activities (item
1.9 above)
(5,029) (24,716)
4.3
Net cash from / (used in) investing activities (item
2.6 above)
(22,715) (33,971)
4.4
Net cash from / (used in) financing activities (item
3.10 above)
(183) 114,365
Consolidated statement of cash flows
Current quarter Year to date
$A’000 $A’000
4.5
Effect of movement in exchange rates on cash
held
(22) (804)
4.6 Cash and cash equivalents at end of period 68,532 68,532
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20)
+ See chapter 19 of the ASX Listing Rules for defined terms.
Page 3
5
Reconciliation of cash and cash equivalents
Current
quarter
Previous
quarter
at the end of the quarter (as shown in the consolidated
statement of cash fl
Share your feedback