Nifty Copper Complex - Pre-feasibility Study
Released
Released
Announcement PDF
ASX ANNOUNCEMENT
27 November 2024
Nifty PFS Confirms $1,129m Pre-Tax NPV and 797kt Ore Reserve
Cyprium Metals Limited (ASX: CYM, OTC: CYPMF) is pleased to present the Prefeasibility Study
(“PFS”) for the Nifty Copper Complex. The PFS confirms the economic viability of large-scale
production of copper in concentrate (“Concentrate Project”) through the refurbishment and
expansion of Nifty’s brownfield concentrator and accompanying new surface mine. The PFS also
confirms economics of producing copper cathode by re-treating Nifty’s Heap Leach Pads 1-6
(“Initial Cathode Project”) which is a subset of oxide opportunities. This PFS supports the first Ore
Reserve Estimate (“ORE”) to be published on the Concentrate Project and Initial Cathode Project
(collectively referred to as the “Projects”).
Highlights on a combined basis include:
•
LOM production of 718kt copper including average annual production of 37.3ktpa over
the first ten years
•
Gross revenues of A$9.2 billion, EBITDA of A$4 billion and pre-tax cash flow of $3.1 billion
on C1 costs of US$2.39 / lb at a long-term copper price assumption of A$13,253/ tonne
•
Brownfield redevelopment costs of $458 million represents 2.3x average EBITDA over
first 10 years of concentrate production
–
Concentrate Project includes capital expenditure of $239 million to refurbish and expand
concentrator and upgrade site infrastructure and capitalised operating costs of $189 million
–
$30 million capital cost for Cathode Project with total project costs of $46 million
•
$1,129 million pre-tax NPV8 ($756 million after-tax); pre-tax IRR of 28.9% (23.6% after-tax)
•
All major permits currently in hand, to be updated using PFS information
•
Concentrate Project Ore Reserves of 83Mt at 0.90% Cu for 753Kt contained Cu
•
Initial Cathode Project Ore Reserves of 10.6mt at 0.41% Cu for 44Kt contained Cu
“The successful completion of this comprehensive PFS marks a pivotal milestone for Cyprium.
This is important, foundational work that we will build on” said Executive Chair Matt Fifield.
“The PFS highlights the long duration and immense profitability of Nifty’s Concentrate Project. With
797,000 tonnes of copper in total reserve supporting more than $3 billion dollars of pre-tax cash
flow, Nifty is a large and important copper source and economic engine for Australia,” said Fifield.
“There are few near-term copper development opportunities that present the scale, longevity and
positive economics of Nifty’s Concentrate Project, and really none that have the speed and cost
advantages of a permitted brownfield site and access to Western Australia’s world-class supply
chain,” added Fifield. “The important information in this PFS serves as a strategic foundation for
our forward activities as we move towards project execution.”
For a copy of this announcement and a short introductory video please visit Cyprium Metals
Investor Hub at https://investorhub.cypriummetals.com/link/drLK0e.
ABN 48 002 678 640
T +61 8 6374 1550
ASX: CYM
Level 1, 437 Roberts Road
Subiaco, WA, 6008
www.cypriummetals.com
Key PFS Metrics
A summary of the key metrics from the Nifty PFS are summarised in Table 2.
Table 1 – Key PFS Metrics
Combined
Concentrate
Project
Cathode
Project
100.4
0.83%
87.7
0.89%
12.7
0.43%
Ore (including inferred)
Grade (including inferred)
% Cu
LOM Production
Average production, yrs 1-10
ktpa Cu
718
37.3
694
38.7
24
5.9
Project Life
Years
20.8
19.8
4.2
LOM Average Copper Price1
A$/ t Cu
13,253
13,252
13,271
Revenue
Selling Costs
Site Operating Costs
EBITDA
A$m
9,194
(1,156)
(4,020)
4,018
8,870
(1,124)
(3,886)
3,860
324
(32)
(134)
158
Development Capital
Capitalised Opex in Development
Sustaining Capital (inc. rehabilitation)
Undiscounted Pre-tax Project Level CF
A$m
A$m
(269)
(189)
(450)
3,110
(239)
(173)
(450)
2,997
(30)
(16)
113
Max Project Drawdown
A$m
(431)
(435)
(46)
A$/ t Pay. Cu
7,461
2.39
7,485
2.40
6,800
2.18
8,110
2.60
8,158
2.62
6,800
2.18
1,042
26.3%
86
110.1%
10,660
7,748
C1 Cost
Mt
kt Cu
A$m
A$m
A$m
A$m
A$m
US$/lb
AISC
A$/ t Pay. Cu
US$/lb
Pre-tax NPV (8%)
Pre-tax IRR
A$m
%
1,129
28.9%
Pre-tax Payback (from first concentrate production) 2
Years
4.75
After-tax NPV (8%)
After-tax IRR
A$m
756
23.6%
Capital Intensity (Dev Capex / Ann Prod)3
Dev Capex / Avg EBITDA4
Max Drawdown / Avg EBITDA 4
A$/t
%
X
X
12,295
2.3x
2.2x
Notes:
1. The PFS valuation has been performed assuming a base case copper price of US$9,370/ t and a long-term foreign exchange
rate of AUD: USD 0.71. The valuation is most sensitive to movements in copper price and FX, both of which have been tested
and presented in the sensitivity analysis section of this report.
2. The payback for the Nifty PFS has been determined with reference to the start of production from the Concentrate Project
3. Capital intensity calculated based on average annual production for years 1-10.
4. Average EBITDA of A$200m per annum is calculated for the Period FY28 – FY37, being the first 10 years of steady state
operations.
Cyprium Metals (ASX:CYM / OTCQB: CYPMF)
Page 2
Table 2 – Ore Reserve Classification for Nifty Projects
Reserve Classification
Proved
Probable
Total
Concentrate
Ore
Cu
(Mt)
(%)
22.7
1.06%
60.6
0.85%
83.3
0.90%
Cu
(kt)
239
514
753
Cathode
Ore
Cu
(Mt)
(%)
10.6
0.41%
10.6
0.41%
Cu
(kt)
44
44
Total
Ore
(Mt)
22.7
71.2
93.9
Cu
(%)
1.06%
0.78%
0.85%
Cu
(kt)
239
557
797
Ore Reserve Estimate Notes:
Supporting information as prescribed in by the JORC Code is included in Table 1, Section 4 of MEC’s report attached to this ASX
announcement, including all material assumptions and modifying factors. The Ore Reserve is based on the current Mineral
Resource Estimate (MRE) for the Concentrate Project as announced on 14 March 2024, and the Cathode Project as announced
on 19 August 2024. The estimated Ore Reserves have been prepared by a competent person in accordance with JORC Code as
detailed in the Competent Persons sign off below. Any conversion of Mineral Resource to Ore Reserve is based on economic
recovery of that material as determined by the mining and processing schedules, capital and operating cost projections,
macroeconomic assumptions, allowances for ore loss and dilution, and any other modifying factors contained in the attached
report entitled “Nifty Copper Complex – Prefeasibility Study” prepared by MEC and disclosed on the date of this release. Please
refer to this report for additional information.
Subsequent Event:
The Final Engineering Date of the PFS was 21 November 2024. On this date, at the Company’s instruction, the basis of design
for the PFS was finalised and further modifications to project engineering and design were stopped. Following the Final
Engineering Date, the Company announced that it had entered into a transaction to sell power generation units as disclosed in
the ASX announcement dated 22 November 2024. This transaction has not been finalised as of the publication date of the PFS.
The Company and MEC Mining note that completion of the sale of the TM-2500 power generation units as contemplated in the
22 November announcement would change the basis of design for power generation for the Concentrate Project. This may have
potential and/or likely impacts to the PFS that include but are not limited to changes to operating costs, capital costs, and project
timing. The impact of any new power generation design would necessarily depend on whether a new selected basis of design
would be and the commercial environment at the time of the selection of the new design.
Neither MEC Mining nor the Competent Person make no representation as to what the impacts of a prospective change in design
basis would have on the financial, operating and temporal results of the PFS based on information as of the Final Engineering
Date. The PFS results should be considered with this context in mind.
Following completion of the transaction discussed here, the Company may choose to update this PFS around a new basis of
design for power supply for the Concentrate Project. The Company does not anticipate material risk from a change in power
supply design, noting the robust Western Australian supply chain of service providers who provide traditional and renewable
power generation equipment, and also supply power supply as a service.
Funding Assumptions:
The Company has formed the view that there is a reasonable basis to believe that requisite future funding for the development of
the Nifty Copper Complex will be available when required.
The grounds on which this reasonable basis is established include (a) positive economic outcomes of the PFS including positive
NPV, IRR above typical funding rates, low Capex / stabilized EBITDA and long project life; (b) lower project implementation r isks
relative to greenfield projects from significant existing infrastructure, prior history of copper production and advanced permitting,
(c) interactions with financing sources and finance advisors prior to the release of the PFS, (d) the significant track record of
senior management and the Board of Directors in raising capital and recent experience in raising capital for the Company and (e)
the potential for the startup of the Initial Cathode Project on a standalone basis.
With regards to funding sources, the Company has conducted extensive non-confidential and confidential market soundings with
multiple financing sources ranging from public equity investors, strategic partners, concentrated equity investors to royalty
financiers, debt financiers, debt advisors, and government-linked funding sources. While there can be no guarantee that these
funding sources will be available at when required, the Company believes that depth of expressed interest from these funding
sources form a reasonable basis to believe that the Company will be successful raising capital for the development of the Nifty
Copper Complex.
The Company notes the senior secured loan facility entered in September 2024 with Glencore reflects both management’s ability
to attract capital and the significant funding appetite that exists for the development of the Nifty Copper Complex. from str ategic
investors
The specific recent history of capital raising by Cyprium Metals demonstrates management capability and interest in the Nifty
Copper Complex. The following ASX announcements relate to recent capital raisings:
Cyprium Metals (ASX:CYM / OTCQB: CYPMF)
Page 3
22/11/2024 – Sale of Surplus Generators
30/09/2024 - Glencore Loan Facility Closed and Offtakes Executed
30/08/2024 - $40M Secured Loan Facility with Glencore
18/09/2023 - $31.6 Equity Raising completed
Board and management have significant experience raising capital for and investing in development stage mining companies, as
can be seen in their biographies on the Company website.
The Nifty Copper Complex as described herein demonstrates that Nifty’s two brownfield processing plants can be developed and
operated at the same time.
PFS Plan: The Company notes that the base planning for the PFS contemplates the coordinated startup of the Concentrate
Project and the Cathode Project. As disclosed below, this results in combined capital expenditures relating to plant, equipment
and infrastructure of $269 million, and further funding of capitalized operating costs which are principally capitalized pre-stripping
of $189 million. The maximum project drawdown is expected to be $431 million. Based on pre-PFS market soundings, the
Company believes that 40% to 60% of the total drawdown can be funded using traditional and government-linked debt financing.
The balance of any project funding requirements would be met through a combination of equity, equity-linked, royalty, project
equity, pre-payment and/or mezzanine loan facilities. Based on the attractive project metrics, low capital intensity, strong
prospective credit metrics emerging from this PFS study as detailed herein and previous market soundings, the Company believes
that there is a reasonable prospect of raising capital for the PFS Plan.
Cathode Project Only: The Company notes that the startup of the Initial Cathode Project is not dependent on the startup of the
Concentrate Project as discussed below. The Company may choose to execute the Initial Cathode Project on a standalone basis,
which would require funding of development capital of $30 million and capitalized operating expenses of $16 million as disclosed
herein. The likely funding sources for the Cathode Project on a standalone basis are equity, equity-linked facilities, royalty
financing, pre-payment and/or loan facilities. The Company believes there is a reasonable prospect of raising sufficient capital to
execute the Cathode Project on a standalone basis given the low total capital requirements, low project complexity and high
potential returns of the Initial Cathode Project.
Cautionary Statement: Despite the Company’s belief in the reasonable prospect of capital availability, it is also possible that
funding may not be available when required. If project funding is not available, then the projects contemplated in this PFS would
not proceed.
Cyprium Metals (ASX:CYM / OTCQB: CYPMF)
Page 4
Concentrate and Initial Cathode Project Design Scope
The Nifty copper complex hosts two standalone brownfield processing plants and has two distinct
sources of ore that can be processed to produce copper products. The PFS has confirmed the
viability of concurrently operating the Concentrator Project with the Initial Cathode Project from a
physical space planning and site interaction standpoint.
A brief description of each project follows.
Concentrate Project Scope
The Concentrate Project design that supports the declaration of economic reserves is focused on
recovering the copper resources as described in the Nifty New Surface Mine Mineral Resource
Estimate released in March 2024. Economics for this project have been developed as follows:
–
Ore suitable for processing through the concentrator is recovered from a new surface mine
via truck-shovel method.
–
Recovered sulphide and transitional ore is processed through the concentrator, as
refurbished and expanded to suit new ore feed volumes of 4.5mtpa. Recovered oxide ore
is stockpiled on Pad 7 (see below) but not processed.
–
Concentrate is produced from the concentrator and shipped to market in containers,
departing site via road transportation to Port Hedland.
–
Waste material remains on site and is deposited in the existing tailings facility as expanded,
and later in integrated waste landforms.
–
Site infrastructure is upgraded to handle the expanded workforce and long life of project.
Figure 1 – Resource wireframe with shell
Figure 2 – Existing Concentrator
Initial Cathode Project Scope
The Initial Cathode Project design that supports the declaration of economic reserves is focused
on recovering the copper resources as described in the Nifty Heap Leach Mineral Resource
Estimate released in August 2024. Economics for this project have been developed as follows:
Cyprium Metals (ASX:CYM / OTCQB: CYPMF)
Page 5
–
Existing material stockpiled on Pads 5 & 6 are turned over to create new surface area.
These materials are retreated in place with fresh leaching solution. Solution pregnant with
copper from the retreatment reports through to existing ILS/PLS collection points.
–
Pregnant solution is pumped to the SX-EW plant as refurbished, where copper in solution
is recovered into marketable cathode product up to rate of ~6ktpa
–
Cathode copper products are shipped by road to Port Hedland for export to market.
–
Now-depleted ore is removed from Pads 5 & 6 and disposed of, uncovering additional
material below, where the process is repeated.
–
Existing Pads 1-4 are moved to a new pad, Pad 7, to accommodate the footprint of the new
surface mine (see Impact of Timing Assumptions on Project Scopes) and retreated using
the same methodology as Pads 5 and 6.
–
All mineralised waste material as described in the August 2024 Nifty Heap Leach MRE (e.g.
material that is thought to contain recoverable copper but for which the Company does not
sufficient information to estimate resource to a JORC standard) is treated as waste,
incurring cost to handle and move when applicable.
Figure 3 – Copper Solution Flowing out of Existing Heap Leach Pads
Figure 4 – Solvent Extraction Plant
Cyprium Metals (ASX:CYM / OTCQB: CYPMF)
Figure 5 – Electrowinning Circuit
Page 6
Impact of Timing Assumptions on Project Scopes
The two projects of the Nifty Copper Complex are both capable of execution on a standalone basis,
however due to physical space constraints the projects interact with each other if they are both in
operation at the same time.
Figure 6 shows the physical site layout, the expected pit limits of the new surface mine supporting
the Concentrate Project, the existing stockpiled material that supports the Initial Cathode Project,
and the location of important infrastructure for the Initial Cathode Project, namely the SX-EW
processing plant.
Figure 6 – Project Interactions
In this Prefeasibility Study, the Initial Cathode Project has been scoped to accommodate the
simultaneous operation of the Concentrate Project as described below.
–
Movement of Pads 1-4: Commencement of surface mining leads to near-term interactions
between the new surface mine and Pads 1-4. The Concentrate Project is assumed to
relocate 3.4 million tonnes of material on Pads 1-4 to new Pad 7 where it is re-treated.
–
Oxide ore from the new surface mine: Oxide ore from the pit is also moved to new Pad
7 for permanent disposal, incurring costs but no revenue.
–
Removal of SX-EW Plant: Figure 7 indicates that the continued advancement of the
surface mine will eventually require the removal and/or relocation of the SX-EW processing
plant. This interaction is not expected to occur until the eighth year of surface mining
operations, allowing for full economic recovery of the ore reserve declared in the Initial
Cathode Project. A change in mining plan assumptions may change the year of interaction
and therefore the likelihood of economic recovery.
With regard to oxide ore from the new surface mine which is stockpiled on Pad 7, the Company
does not have sufficient information to evaluate the economics of further treatment of this material
at a PFS level of certainty and has therefore excluded any operations to recovery copper from the
overall Initial Cathode Project design.
Cyprium Metals (ASX:CYM / OTCQB: CYPMF)
Page 7
Concentrate Project Summary
The Concentrate Project is, as previously described, a large truck-shovel operation that targets the
approximately 1 million tonnes of copper metal in transitional and sulphide resources as feed for a
concentrator. For additional information on the resource base, please refer to the March 2024
Nifty New Surface Mine MRE.
Resource Conversion
The Production Target for the Concentrate Project are primarily Measured and Indicated resources
of 83.3Mt @ 0.90% (97% of total copper processed). Inferred material of 4Mt @ 0.56% Cu that falls
within the Ore Reserve Pit is assumed in the Concentrate Project. There is a low level of geological
confidence associated with Inferred Mineral Resources and there is no certainty that further
exploration work will result in the determination of Indicated Mineral Resources (or Ore Reserves)
in relation to that mineralisation.
Table 3 summarises the total Production Target for the Concentrate Project by JORC resource
classification, and the percentage of the total Nifty new surface mine mineral resource that has
been converted into the PFS mine plan.
Table 3 - Production Target Resource Basis, Concentrate Project
Resource
Area
Surface Mine
Surface Mine
Surface Mine
Surface Mine
Resource
Classification
Measured
Indicated
Inferred
Total
Million
Tonnes
22.7
60.6
4.4
87.7
%Cu
1.06%
0.85%
0.56%
0.89%
Cont. Cu (kt)
239
514
25
778
% in PFS
Economics
31%
66%
3%
100%
% of Total
MRE
64%
81%
88%
75%
Note: Please see modifying factors in the attached modifying factors in attached PFS Report prepared by MEC Mining.
Ore Reserve – Concentrate Project
The Ore Reserve for the Concentrate Project (refer Table 4) were declared based on a PFS-level
mine plan and economics. The plans that support the determination of economic recovery are
summarised in the ensuing sections and the accompany technical report prepared by MEC.
Table 4 – Ore Reserve Classification for Concentrate Project
Reserve Classification
Proved
Probable
Total
Concentrate Project
Ore
Cu
(Mt)
(%)
22.7
1.06%
60.6
0.85%
83.3
0.90%
Cu
(kt)
239
514
753
Note: Supporting information as prescribed in by the JORC Code is included in Table 1, Section 4 of MEC’s report attached to
this ASX announcement, including all material assumptions and modifying factors. The Ore Reserve is based on the current
Mineral Resource Estimate (MRE) for the Concentrate Project as announced on 14 March 2024. The estimated Ore Reserves
have been prepared by a competent person in accordance with JORC Code as detailed in the Competent Persons sign off below.
Any conversion of Mineral Resource to Ore Reserve is based on economic recovery of that material as determined by the mining
and processing schedules, capital and operating cost projections, macroeconomic assumptions, allowances for ore loss and
dilution, and any other modifying factors contained in the attached report prepared by MEC and disclosed on the date of this
release. Please refer to this report for additional information.
Cyprium Metals (ASX:CYM / OTCQB: CYPMF)
Page 8
Concentrate Production Profile
Figure 7 below shows the anticipated production profile from the Concentrate Project. The
Concentrate Project shows a 20-year life, with life of mine production of 694,000 tonnes and an
average production of 38,700 tonnes of copper across the first ten years of project life. Table 5
below summarises life of mine physicals for the Concentrate Project.
Figure 7 – Copper in Concentrate Production
kt
50
45
40
35
30
25
46 46
46
20
35
34
15
39
41 41
39
35 33
28
43 44 44
35
22
10
14 14
12
5
-
3
-
-
FY48
FY47
FY46
FY45
FY44
FY43
FY42
FY41
FY40
FY39
FY38
FY37
FY36
FY35
FY34
FY33
FY32
FY31
FY30
FY29
FY28
FY27
FY26
Copper in Concentrate
Table 5 – Concentrate Project, Physicals Summary
Waste Mined
Ore Mined
Strip Ratio
Mt
Mt
W:O
614.9
87.7
7.0
Design Plant Throughput
Average Plant Throughput
Mtpa
Mtpa
4.5
4.4
Total Concentrator Feed
Average Copper Grade
Metallurgical Recovery
Mt
% Cu
%
87.7
0.89%
89%
LOM Production
t Cu
mm lbs Cu
694,000
1,529
Avg. Annual Production, Years 1-10
tpa Cu
lbs Cu
38,700
85 million
Avg. Annual Production, LOM
tpa Cu
lbs Cu
35,100
77 million
Cyprium Metals (ASX:CYM / OTCQB: CYPMF)
Page 9
Surface Mine Operating Plan
The Concentrate Project establishes a new surface mine to access the sulphide and transitional
ore within the pit shell.
–
Speed to Ore: Per the Company’s current engineering knowledge base suitable to support
a PFS, the constraint on achieving regular concentrate production is availability of the
concentrator (currently estimated at 17 months) rather than the mine availability. The PFS
mining rates were designed to match pre-stripping activity with concentrator availability.
–
Operating Philosophy:
The Concentrate Project assumes contract operations
throughout. The economic model includes contractor margin of ~15% on top of all
operating costs, and a capital recharge component on all equipment.
–
Mining Fleet: Primary waste stripping is achieved through use of 600-tonne excavators,
and ore mining is executed with 200-tonne excavators. Both waste and ore haulage is
designed with 220-tonne trucks, which is incorporated in all ramp and road design widths.
–
Zone of Influence: There is a “zone of influence” where surface mining activities will
directly or indirectly overmine previous underground workings and/or the ground being
mined is within a geotechnical domain that is influenced by previous underground
workings. Substantial mapping and reconciliation of mine records was completed as a part
of the March MRE, Geotechnical drilling, mapping and engineering design specific to these
areas was completed as a part of this PFS. The overall mine plan was developed with
consideration for the zone of influence. Each phase specifically seeks to balance ore and
waste movements from areas within the zone of influence with areas that can be considered
undisturbed. Unit operating rates and certain operating costs were also adjusted to
account for changed operating protocols within the zone of influence, and these rates and
costs were discussed with a contract operator with significant and relevant experience.
–
Pit Design and Material Movements
Figure 8 shows the PFS material movement is front-loaded as the existing shallow pit that
previously supported oxide operations is cut back significantly to access the sulphide ores. Figure
11 below shows the planned pit progression, and Figure 12 a typical cross-sectional view of the
targeted resources within the pitshell.
Cyprium Metals (ASX:CYM / OTCQB: CYPMF)
Page 10
Figure 8 – Mine: Total Material Moved
kt
90,000
80,000
70,000
60,000
50,000
40,000
30,000
20,000
10,000
FY44
FY43
FY42
FY41
FY40
FY39
Ore
FY38
FY36
FY37
FY35
FY34
FY33
FY32
FY31
FY30
FY29
FY28
FY27
FY26
Waste
Ore Movements
Figures 9 and 10 below show the PFS mine plan is designed to deliver 3-6 million tonnes of ore,
and higher-grade ore is processed in the period while lower grade ores are stockpiled and blended
into ore feed over time. The balance of the low-grade stockpile is processed in the final years of
the PFS plan. Table 6 below shows overall plant performance underlying the PFS, with 89%
projected recovery.
Figure 9 – Mine: Ore Mining Schedule
kt
% Cu
8,000
1.1%
7,000
1.0%
1.0%
0.9%
0.9%
6,000
0.8%
1.1%
1.2%
1.1%
1.0%
1.0%
0.9%
0.9%
0.8%
0.8%
0.8%
0.8%
0.7%
5,000
0.8%
0.7%
4,000
0.6%
3,000
0.4%
2,000
0.2%
1,000
-
0.0%
FY44
FY43
FY42
FY41
FY40
FY39
FY38
FY37
Transitional
FY36
FY35
FY34
Cyprium Metals (ASX:CYM / OTCQB: CYPMF)
FY33
FY32
FY31
FY30
FY29
FY28
FY27
FY26
Fresh
Copper Grade
Page 11
Figure 10 – Plant: Ore Feed
kt
%Cu
5,000
1.40%
4,500
1.1% 1.1%
1.1%
4,000
1.0%
1.0%
0.9%
3,500
0.9%
3,000
1.20%
1.1% 1.1% 1.1%
1.0% 1.0%
1.0%
0.9%
1.00%
0.9%
0.8%
0.80%
0.7%
2,500
0.6%
0.60%
2,000
0.4% 0.4% 0.4%
1,500
0.40%
1,000
500
0.20%
0.0%
0.0%
-
0.00%
FY48
FY47
FY46
FY45
FY44
FY43
FY42
FY41
FY40
FY39
FY38
FY37
FY36
FY35
FY34
FY33
FY32
FY31
FY30
FY29
FY28
FY27
FY26
Concentrator Feed Tonnes
Concentrator Feed Grade
Table 6 – Metallurgical Recoveries, Concentrate
Material Type
Feed
(kt)
Feed
(kt Cu)
Grade
(%Cu)
Recovery
(%)
Produced
(kt Cu)
Transitional
894
6
0.64%
76%
4
Fresh
86,800
772
0.89%
89%
689
Total
87,694
778
0.89%
89%
694
Waste Haulage and Location
Waste material will be initially used to build up the existing tailings dam to accommodate additional
tailings disposal, later to form up integrated waste landforms, and finally building a waste rock
storage facility on the south side of the open pit, as the sequence in Figure 13 shows.
Figure 14 displays areas currently permitted for clearing of native vegetation. These permitted
areas are in addition to mine areas that are already cleared. The permitted areas are suitable to
accommodate ~93% of all waste material produced in the PFS mine plan.
Permitting
The major permits required to commence the Concentrate Project are largely complete. Table 7
shows the status of these. With the Concentrate Project now supported by a PFS, the Company
will work to complete all renewals and update existing approvals with current information.
Cyprium Metals (ASX:CYM / OTCQB: CYPMF)
Page 12
•
Figure 11 – PFS Pit Design and Sequencing
Stage 1
Stage 2
Stage 3
Stage 4
Stage 5 - Final
Figure 12 – Cross sectional view
Cyprium Metals (ASX:CYM / OTCQB: CYPMF)
Page 13
•
Figure 13 – PFS Integrated Waste Landform Design and Sequencing
Stage 1
Stage 2
Figure 14 – Native Vegetation Clearing Permit
Cyprium Metals (ASX:CYM / OTCQB: CYPMF)
Stage 3
Stage 4
Stage 5 - Final
Table 7 – Permits Status Required for Operation
Permit
Regulator
Current
Status
Renewal
/
Requirements
Works Approval
DWER
Approved
Aug-25
Native Veg. Clearing (3)
DEMIRS
Approved
Various
Mining Proposal
DEMIRS
Approved
MOP Update
Mine Closure Plan
DEMIRS
Approved
Apr-25
Water License
DWER
Approved
Apr-26
Page 14
All-in-Sustaining Costs (AISC)
The operating cost structure of the Concentrate Project is summarized below in Table 8. These
operating costs were built from first principles at a PFS level of confidence and assume a contractor
mining model. Additional information on these costs can be found in the accompanying technical
report. A breakdown of all-in-sustaining costs (AISC) for the Concentrate Project is summarised
in Table 8.
Table 8 – AISC Summary, Concentrate Project
A$/ t Pay. Cu
A$/ t ore processed
US$ /lb. Pay. Cu
Copper Price
13,252
101.1
4.25
Mining Cost
Processing Cost
Site G&A
Selling Cost
Cash Cost
2,561
3,063
181
1,679
7,485
19.5
23.4
1.4
12.8
57.1
0.82
0.98
0.06
0.54
2.40
Sustaining Capital (including Rehab)
All-in-Sustaining Cost
672
8,158
5.1
62.3
0.22
2.62
Note: Selling costs include road transport, ocean freight, insurance, port charges, TCRCs, marketing fees and state government
royalites.
Sustaining capital allowances have been provided to allow for the ongoing costs of repairing
existing process plant, including structural concrete, electrical and platework repairs. Sustaining
capital has also been forecast for progressive tailings storage lifts and rehabilitation costs have
been included at the end of the life of the Concentrate Project.